Order
Heard Mr. D.C. Roy, learned counsel appearing for the
revision petitioners as well as Mr. R. Saha, learned counsel
appearing for the respondents.
This is an application filed under Article 227 of the
Constitution of India asking this Court to exercise its power of
superintendence against the order dated 21.11.2019 passed by
the learned Civil Judge, Senior Division, Court No.2 in T.S.
(Partition) 178 of 2013.
At the very outset, learned counsel appearing for the
petitioners has drawn my attention to the order dated
21.11.2019 which is under challenge.
The order speaks as follows:-
“ 21.11.2019-
Ld. Counsel Mr. R. Choudhury is present
for the plaintiffs.
Page 2 of 6
Received one report from the Survey Commissioner
Sri Pravat Debnath in compliance with the order dated
01-10-2019.
Ld. counsel Mr. R. Choudhury has filed photocopies
of the order dated 11-12-2015 and 16-01-2016 passed
by this court in this suit along with photocopy of one
complaint made before the SP, West Tripura dated 05-
10-2013.
Heard Ld. Counsel Mr. R. Choudhury who submitted
that when the Survey Commissioner revisited the
decretal land in compliance with the order dated 11-09-
2019 then he has been resisted by the defendant no. 2
Rakesh Ch. Debnath and as such pillars could not be
posted by the plaintiffs at their share at the decretal
land. Ld. Counsel further submitted that on 11-12-2014
an application was filed by the plaintiffs for engagement
of Police personnel for assistance of the Survey
Commissioner for partition by metes and bounds.
Subsequently, as per order dated 16-01-2016 the said
application seeking police help was kept reserved by this
court and till date no order has been passed.
Hence, Ld. Counsel Mr. R. Choudhury has prayed
for passing necessary order on the above mentioned
application so that the Survey Commissioner may visit
the decretal land in presence of Police personnel and to
avoid any resistance from the defendants.
Considered.
At the very outset, I would like to mention that this
is a final decree proceeding of a partition suit and not an
execution proceeding of the final decree.
In this case the report of the Survey Commissioner
dated 18-08-2018 making a partition proposal by metes
and bounds was initially opposed by the plaintiffs and
after hearing the submission of the plaintiffs regarding
objection against the Commissioner's report as per order
dated
31-07-2019
the
Survey
Commissioner
was
directed to revisit the decretal land to clarify certain
points raised in the objection by the plaintiffs and to
submit a supplementary report. Thereafter, on 11-09-
2019 it was submitted by the plaintiffs that after
reconsideration
of
the
report
of
the
Survey
Commissioner and the order dated 31-07-2019 passed
by this court the plaintiffs have decided to accept the
Commissioner's report dated 18-08- 2018 containing the
partition proposal. But the plaintiffs prayed that the
Survey Commissioner shall again visit the decretal land
and in his presence the plaintiffs shall post pillars in their
Page 3 of 6
respective share at the decretal land. But now from the
submission of Ld. Counsel for the plaintiffs and the
report of the Survey Commissioner submitted today it
appears to the court that if at this stage Survey
Commissioner revisits the decretal land then he may be
resisted by the defendants.
The drawl of final decree in a partition suit through
engagement of a Commissioner is a ministerial act. In
the final decree proceeding of partition suit the scope of
the court is limited to the extent of appointment of a
Survey Commissioner as per Or. XXVI Rule 13 of CPC to
make partition through the Commissio