Sanjay Narang – Appellant
Versus
Jakir Hussain – Respondent
CLCON 431/2018
IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
Civil Contempt Petition No. 431 of 2018
Sanjay Narang
....... Petitioner
Vs.
Shri Jakir Hussain
…....Respondent
Mr. Aditya Singh, Advocate for the petitioner.
Mr. B.S. Adhikari, Advocate for the respondent.
Hon’ble Sudhanshu Dhulia, J. (Oral)
This is a contempt petition filed by the
petitioner alleging that the respondent has willfully and
deliberately violated the order of this Court dated
10.01.2018 passed in Review Application No.941 of 2017
in Special Appeal No.645 of 2014.
2.
This case has a chequered history. The
petitioner had raised a construction in the Cantonment
area, which was against the bye-laws of the Cantonment
Board as well as against the Works of Defence Act, 1903.
3.
The case of the Cantonment Board was that
firstly the petitioner had raised the construction within 50
meters of a defence establishment, and hence violated the
Works of Defence Act, 1903. In any case, since the
construction raised by the petitioner was not authorized
under the Cantonment Act, 2006, a demolition order was
passed. Consequently, a writ petition being WPMS
No.2609 of 2014 was filed by the petitioner before this
Court which was dismissed by this Court on 27.11.2014,
2
against which, a special appeal being SPA No.645 of 2014
was filed by the petitioner, which was also dismissed by a
Division Bench of this Court vide order dated 05.09.2017.
4.
As far as the construction which was within 50
meters of the defence establishment was concerned, there
was no ambiguity in the order of the Division Bench and
the demolition was carried out, but the remaining
construction
which
was
beyond
50
meters,
the
Cantonment Board was to wait for a period of three
months before carrying out the demolition.
5.
The only question was from when the three
months period was to be calculated, whether it would be
calculated from 10.01.2018 when the Division Bench had
passed the order or from the date when the actual
measurement was carried out which was ultimately done
on 20.03.2018. The operative portion of the Division
Bench order dated 10.01.2018 is as follows:-
“We are of the view that the review is
to be partly allowed and the impugned notice
(Annexure - 2) in relation to Building No. 2 and
structures, namely, Building No.6 falling under
Building No. 2 will stand quashed. This we do
for the purpose of carrying out measurement
from the Work under the Defence of India
Rules. Respondent Nos. 3 & 4 will carry out the
measurement. If it is found that the structures
are within 50 meters, they will be free to carry
out the demolition as per the notice. In case, it
is found that it is beyond 50 meters, then the
respondent Authorities will wait for a period of
three months and this is in view of the
pendency of the challenge against the order
setting
aside
the
sanction
order
dated
30.06.2012.”
(Emphasis Provided)
6.
It is true that on clarification sought by the
petitioner as to from when the three months period would
start, the Division Bench of this Court vide order dated
3
17.05.2018 later clarified that three months period would
start from 20.03.2018. This clarification was done on
17.05.2018. However, by this time, the demolition had
already been carried out. The petitioner, therefore, has
filed the present contempt petition before this Court
saying that the order dated 10.01.2018 passed by the
Division Bench of this Court has been deliberately and
willfully disobeyed, inasmuch as, the demolition was
carried out before the period of three months.
7.
The reason why three months period was
granted to
the petitioner obviously was that the
petitioner’s
prayer
against
the
construction
and
demolition was pending before this Court in a writ petition
being WPMS No.07 of 2017, in which time was given to
the petitioner
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.