HIGH COURT OF UTTARAKHAND
MS SARTHI CONSTRUCTION AND INFRA PRIVATE LIMITED A PRIVATE LIMITED – Appellant
Versus
STATE OF UTTARAKHAND – Respondent
WPMB 119 / 2026
I N THE HI GH COURT OF UTTARAKHAND AT NAI NI TAL THE HON’BLE CHI EF JUSTI CE MR. MANOJ KUMAR GUPTA AND THE HON’BLE JUSTI CE MR. SUBHASH UPADHYAY Writ Petition (M/B) No.119 of 2026
25 February, 2026 M/s Sarthi Construction and Infra Private Limited and Another -----Petitioners Versus State of Uttarakhand and Others ----Respondents ----------------------------------------------------------------------
Presence:-
Mr. D.S. Patni, learned Senior Counsel assisted by Mr. Dharmendra Barthwal, learned counsel for the petitioners.
Mr. Yogesh Chandra Tiwari, learned Standing Counsel for the State of Uttarakhand/ respondent no.1.
Mr. Aditya Pratap Singh, learned counsel for Uttarakhand Pollution Control Board/ respondent no.2.
Mr. Manoj Kumar, learned Standing Counsel for the Union of India/
respondent no.3.
----------------------------------------------------------------------
JUDGMENT : (per Mr. Manoj Kumar Gupta C. J.
1. Petitioner no.1 is a private limited company and petitioner no.2 is Director of the petitioner company. The petitioner company along with another company M/s VRS Infra Pvt. Ltd. has formed a joint venture in the name and style of ‘M/s Sarthi Construction and Infra Private Limited – M/s VRS Infra Pvt. Ltd. (JV)’. The said JV has been granted an important strategic work – ‘Improvement /Construction of 2-Lane with hard shoulder of Askote-Lipulekh Road From Tawaghat Village to Budhi Village (Design Km.56.935 to Km.95.748) and from End of tunnel Portal to Kalimandir (Design Km. 113.828 to Km.133.078)(Total Design Length = 58.063 Km.) of (NH- 09) under Project Hirak of BRO in the State of Uttarakhand on EPC Mode, (Tender ID:- 2023_MoRTH_740109_2)’ by the Boarder Road Organization(BRO), Headquarter, Chief Engineer, Project Hiark vide letter of acceptance dated 07.09.2024.
2. The case of the petitioners is that the JV in view of it have been granted the aforesaid work sought permission for installation of a temporary mobile crushing plant. The road which is to be constructed under the project is a border road and, therefore, the project is of strategic importance.
3. The application of the petitioners has not been entertained in view of head office letter dated 27.05.2025 which directs that no application for setting up of any new stone crushing unit shall be entertained. The said order was issued by the head office in order to ensure compliance of an order dated 22.05.2025 passed in WPMB No.281 of 2025, ‘Mahendra Singh & Another Vs. Union of India & Others’. The operative part of the order passed in WPMB No.281 of 2025 is extracted below for ready-reference:
“13. We, therefore, call upon the Secretary, Mining, Government of Uttarakhand and Uttarakhand Pollution Control Board to identify areas in every district, which can be earmarked as dedicated zones for crushing and dumping of stones/RBM, within six weeks from today. We hope and expect that till the exercise of identification of such area is complete, permission for setting up new stone crushing units may be kept on hold”
4. The specific case of the petitioners is that the mobile crushing unit which it proposes to set up is of a temporary nature for captive use during the construction of the road and after completion of the project the unit would be dismantled.
5. The further case of the petitioners is that if the petitioners are not granted permission to set up the mobile crushing unit it would not be able to meet its commitments under the contract and it would also be detrimental to the national interest.
6. Learned Senior Counsel for the petitioners has referred to an order dated 30.12.2025 passed in the same PIL (WPMB No.281/2025) whereby the intervention application filed by the State seeking permission to set up a temporary mobile crushing plant for Jamrani Dam Multipurpose Project was allowed considering the fact that the permission sought was for a temporary mobile crushing project for captive use only.
7. We find force in the submission of learned Senior Counsel for the petition
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.