HIGH COURT OF UTTARAKHAND
MOHMAD AABID – Appellant
Versus
NATIONAL HIGHWAY AUTHORITY OF INDIA – Respondent
WPPIL 23 / 2025
Office Notes, reports, orders or proceedings SL.
Date or directions No and 2025:UHC:1285-DB Registrar’s order with COURT’S OR JUDGES’S ORDERS Signatures
24.02.2025 WPPIL No. 23 OF 2025 Hon'ble G. Narendar, C.J.
Hon’ble Ashish Naithani, J.
Heard Mr. Rohit Kumar, learned counsel for the petitioner, Mr. Naresh Pant and Mr. Raunak Pant, learned counsels for respondent no.1 and Mr. Amarendra Pratap Singh, learned Additional Advocate General for the State of Uttarakhand.
2. On the previous date of hearing, learned counsel for respondent no.1- National Highways Authority of India had produced a compilation of papers. One letter is addressed to the counsel on record and same reads as under:-
“NHAI/ PIU-VV/ Court Case (HC)/ 2020/ 8403 Dt. 19.02.2025 To, Sh. Naresh Pant, Advocate, 254, Cheena Khanline, Pin Code- 263001. Mob: 9411167564 E-mail: Nareshpant_advocate@rediffmail.com Sub: Regarding WP (PIL) titled as Mohmad Aabid Vs.
NHAI & Others.
Sir, Kindly refer your e-mail dt. 16.02.2025 vide which writ petition PIL titled Mohmad AabidVs NHAI & Others regarding demand of underpass in Vill- Hasanpur has been forwarded to this office.
In this regard, a brief note along with drone photographs & line diagram is herewith enclosed with the request to defend in the matter on behalf of NHAI to safeguard the interest of Authority.
Thanking you. Your faithfully Encl: As above (Rahul Meena)
Manager (Tech.)
For Project Director PIU- Vasant Vihar (Dehradun).”
3. At Page Nos.2 and 3 of the said letter, brief note and photographs captured by the drone are enclosed, and at Page No.4, a short note is appended. Page No.4 reads as under:-
Name of the project:- Up-gradation & Four Laning of Poanta Saheb- Ballupur section of NH-72 In the State of Uttarakhand under NH(0) on Hybrid Annuity Mode. Package-II: Mednipur- Ballupur from Design Ch. 18.700 to Ch. 44.800 Brief w.r.t demand of underpass in Hasanpur Village at Km 28+440.
The subject project starts from Km 18+700 & ends at 44+800 having total length of 26.10 Kms, Now, out of total 26.10 kms, 22.00 Kms is a Greenfield highway/new alignment passing through crop fields. Accordingly, there are regular demands of underpasses & Culverts by Villagers.
2. The construction work was started by Concessionaire w.e.f 18.02.2023 having Scheduled Completion Date as 17.02.2025 i.e. 02 Years. Currently, the actual progress of the project is to the tune of 75.00% & it is expected that project shall be completed in next 04 Months.
3. In 22.00 Km of Greenfield stretch, number of structures in original agreement & additional structures provided based upon site requirement/public demand is tabulated as under:
S.no Structure In Additional original approved as Agreemen per public t (in nos.) demand/
site requirement (in nos.)
1. Culverts 73 07 2. Underpas 07 04 s
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.