HIGH COURT OF UTTARAKHAND
Hon'ble Mr. Justice Manoj Kumar Tiwari
2006 Shaukat Ali … Petitioner – Appellant
Versus
Deputy Director – Respondent
HIGH COURT OF UTTARAKHAND AT NAINITAL Writ Petition (M/S) No. 376
IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
Writ Petition (M/S) No. 376 of 2006
Shaukat Ali
… Petitioner
Vs
Deputy Director of Consolidation & others
… Respondents
Mr. M.S. Tyagi, Advocate for the petitioner.
Mr. P.S. Bisht, learned Standing Counsel for the State of Uttarakhand.
Hon’ble Manoj K. Tiwari, J. (Oral)
1.
By means of this petition, under Article 227 of the
Constitution of India, petitioner has challenged the orders
dated 14.01.1997 & 14.02.1997 passed by Settlement Officer
Consolidation, Haridwar and also the order passed by Deputy
Director of Consolidation, Haridwar on 28.12.2005.
2.
According to the petitioner, Land Management
Committee Bijholi allotted a Patta of land in his favour
comprised in Khasra No. 121 admeasuring 2 bigah 2 biswa
situate at Village Bijholi, Tehsil Roorkee, District Saharanpur
on 14.08.1974 and he is in possession over the said land ever
since then. He further submits that upon commencement of
consolidation proceedings, the said land was recorded as Zohar
(Pond) and petitioner filed an objection under Section 9A(2) of
U.P. Consolidation of Holdings Act, 1953 (hereinafter referred to
as “Act”) contending that the aforesaid land was allotted by
Land Management Committee Bijholi to him, therefore, his
name be mutated as Bhumidhar. The Consolidation Officer
allowed the objection filed by the petitioner and passed an
order dated 20.02.1996 for recording the name of the petitioner
as Bhumidhar under Section 122-B (4F) of Uttar Pradesh
Zamidari Abolition and Land Reforms Act, 1950 (in short
“UPZA&LR Act”).
2.
The Gram Sabha Bijholi challenged the order passed
by Consolidation Officer, Roorkee by filing an appeal on
25.05.1996 under Section 11(1) of the Act. A delay
2
condonation application was also filed seeking condonation of
delay in filing the appeal. Petitioner filed objection against the
delay condonation application and learned appellate court
(Settlement
Officer
Consolidation)
allowed
the
delay
condonation application, vide order dated 14.01.1997.
3.
Petitioner challenged the order dated 14.01.1997
passed on the delay condonation application by filing revision
No. 278 of 2005-06, under Section 48 of the Act, before Deputy
Director of Consolidation, Haridwar. While the aforesaid
revision petition was pending, learned Settlement Officer
Consolidation allowed the appeal and set aside the order
passed by Consolidation Officer, vide judgment and order dated
14.02.1997 on the ground that petitioner does not belong to
Scheduled Caste or Scheduled Tribes, therefore, he cannot be
given benefit of Section 122-B(4F) of UPZA&LR Act and further
that there is no material on record to show that the land in
question was validly allotted in favour of the petitioner.
Learned Settlement Officer Consolidation further held that land
in question is a pond which belongs to Gram Sabha, therefore,
it would be unjust to give any right in respect of pond land to a
private individual.
4.
Thus feeling aggrieved by the order passed by
Settlement Officer Consolidation on 14.02.1997, petitioner filed
revision No. 279 of 2005-06, which was dismissed by learned
Deputy Director of Consolidation along with Revision Petition
No. 278 of 2005-06 filed by the petitioner, vide judgment and
order
dated
28.12.2015.
Learned
Deputy
Director
of
Consolidation held that the land in question is recorded as
Zohar (Pond) in revenue record, therefore, Bhumidhari rights
cannot accrue over the same in view of provision contained in
Section 132(A) of UPZA&LR Act. It was further held that
petitioner is not entitled to benefit of Section 122-B(4F) of the
3
UPZA&LR Act, as he does not belong to Scheduled Caste or
Scheduled Tribes.
5.
Heard Mr. M.S. Tyagi, learned counsel for the
petitioner, Mr. P.S. Bisht, learned Standing Counsel for the
State and perused the record.
6.
Mr.