IA No. 1830 OF 2020 IN DFR No. 462 of 2020
1 | P a g e
IN THE APPELLATE TRIBUNAL FOR ELECTRICITY
(Appellate Jurisdiction)
IA No. 1830 OF 2020 IN DFR No. 462 of 2020 &
IA No. 1832 OF 2020
Dated : 12th August, 2021
Present : Hon`ble Mrs. Justice Manjula Chellur, Chairperson
Hon`ble Mr. Ravindra Kumar Verma, Technical Member
In the matter of:
1.
2.
3.
Amreli Power Projects Ltd.,
Represented by Authorised Signatory
10th Floor, Sangeeta Complex,
Near Parimal Crossing, Ellisbridge,
Ahmedabad - 380006, Gujarat
Bhavnagar Biomass Power Projects Pvt.
Ltd.
Represented by Authorised Signatory
10th Floor, Sangeeta Complex,
Nr. Parimal Crossing, Ellisbridge,
Ahmedabad - 380006, Gujarat
Junagadh Power Projects Pvt. Ltd.
Represented by Authorised Signatory
10th Floor, Sangeeta Complex,
Near Parimal Crossing, Ellisbridge,
Ahmedabad - 380006, Gujarat
…Appellant No.1
…Appellant No.2
…Appellant No.3
VERSUS
1.
Gujarat
Electricity
Regulatory
Commission
Through its Secretary,
6th Floor, GIFT ONE, Road 5C,
Zone 5, GIFT City,
Gandhinagar – 382355, Gujarat, India.
...Respondents No. 1
2.
Gujarat Urja Vikas Nigam Ltd.
Through its Managing Director,
IA No. 1830 OF 2020 IN DFR No. 462 of 2020
2 | P a g e
Sardar Patel Vidyut Bhawan,
Race Course Road,
Vadodra, 390007.
...Respondents No. 2
Counsel for the Appellant(s) :
Mr. Amit Kapur
Ms. Poonam Verma
Mr. Saunak Kumar Rajguru
Ms. Adishree Chakraborty
Ms. Aparajita Upadhyay
Ms. Sakshi Kapoor
Ms. Noor Shergil
Mr. Pratibhanu Singh
Counsel for the Respondent(s) :
Mrs. Suparna Srivastava for R-1
Ms. Ranjitha Ramachandran
Ms. Poorva Saigal
Ms. Anushree Bardhan
Mr. Shubham Arya
Ms. Tanya Sareen
Mr. Arvind Kumar Dubey for R-2
ORDER
PER HON’BLE MR. RAVINDRA KUMAR VERMA, TECHNICAL
MEMBER
1. Proceedings
of
this matter
are
conducted
through
video
conferencing.
2. The instant Application has been filed by the Applicants/Appellants
along with Appeal under DFR No. 462 of 2020 for condonation of 967
days delay in filing the instant Appeal. The present Appeal is filed
under Section 111 of Electricity Act, 2003 against the Order dated
15.03.2018 in OP No. 01 of 2018 in ‘Determination of Tariff for
IA No. 1830 OF 2020 IN DFR No. 462 of 2020
3 | P a g e
Procurement of Power by the Distribution Licensees and Others from
Biomass based Power Projects and Bagasse based Co-generation
Projects for Control Period upto FY 2019-20 passed by the Gujarat
State Electricity Regulatory Commission.
3. After hearing the learned counsel on both sides and also going
through the written submissions filed by them our opinion is given in
following paragraphs.
4. The instant application has been filed by the Applicants/Appellants
for condonation of 967 days delay in filing the instant appeal. The
issue in appeal is regarding determination of tariff and procurement
of power by distribution licensees and others from Biomass based
power projects and bagasse based co-generation projects for control
period upto FY 2019-20 passed by the Gujarat State Electricity
Regulatory Commission. The Applicants/Appellants owns a biomass
power plant which it acquired much after the bar of limitation came
into effect from the erstwhile promoters after 29.04.2018 (i.e. the date
when the 45 day period to file the appeal ended). Before that the
plants had remained shut for a prolonged period (over 5 years
between 2013-2018) due to litigations. The case of the
Applicants/Appellants is that it acquired the plants from the promoters
IA No. 1830 OF 2020 IN DFR No. 462 of 2020
4 | P a g e
after the 45 days period to file the appeal had ended. The
Applicants/Appellants has explained that it took time for the
Applicants/Appellants to gather the operational experience by
operating the plant for some time an
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.