SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(CERC) 57

CENTRAL ELECTRICITY REGULATORY COMMISSION
Shri Jishnu Barua, CJ, Shri Ramesh Babu V., J, Shri Harish Dudani, J, Shri R.S. Dhillon, J
Measures to mitigate the risks on the power system under Clauses (2) and (3) of the Regulation 30 of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations 2023.
2/SM/2025



The judgment emphasizes the need for operational flexibility in power generation to maintain grid frequency within regulatory limits, highlighting the importance of two-shift operations for thermal units and incentivizing renewable energy sources.

Headnote:(A) Indian Electricity Grid Code, 2023 - Regulation 30 - High-frequency operation in power system - Report by Grid-India indicated persistent high-frequency operation on 4th, 11th, and 25th August 2024, with frequency exceeding 50.05 Hz for significant portions of the day - Factors contributing included suppressed demand, over-injection by renewable energy sources, and inadequate flexibility from thermal stations - Measures suggested for enhancing grid flexibility included operationalizing two-shift operations for thermal units and incentivizing flexible operations. (Paras 1-6, 14-32)

(B) Frequency Control - The National Reference Frequency is 50.000 Hz, with an allowable band of 49.900-50.050 Hz - All users must adhere to their schedules to maintain grid frequency within the specified band. (Paras 7-8)

(C) Over-injection and Under-drawl - High frequency attributed to over-injection by thermal and renewable energy generators, and under-drawl by states - The need for operational adjustments and adherence to minimum turn-down levels emphasized. (Paras 24-30)

(D) Pilot Project - A pilot project for two-shift operations of selected thermal units is directed to be identified and implemented to address operational challenges. (Paras 18-22) (E) Directions - The Commission directed NLDC to implement measures for frequency control and operational efficiency, including incentivizing renewable energy sources for ancillary services. (Paras 32-34)

Order

Background:

1. Grid-India, vide its letter dated 17.09.2024, submitted a Report to the Commission on high-frequency operation on 4th, 11th, and 25th August 2024. Grid-India, in its report, submitted that persistent high-frequency operation was observed on the 4th, 11th, and 25th of August 2024 in India’s power system, with frequency remaining above 50.05 Hz for around 26%, 33%, and 38% of the time during the day, respectively. The key highlights with regard to high frequency of the grid on 4th, 11th and 25th August 2024 are as under:

Metric04 Aug 202411 Aug 202425 Aug 2024
% of time frequency remained above 50.05 Hz26.2733.3237.97
Duration of continuous high frequency (>50.05 Hz) in minutes226120258
Maximum instantaneous frequency (Hz) and its time of occurrence (hh:mm)50.39 (12:02)50.33 (13:44)50.38 (13:07)

2. As per Grid-India’s Report, the contributing factors for high-frequency operation in the Indian power system on 04, 11, and 25 August 2024 are listed below:

a) Suppressed demand due to widespread rains and weekend b) Over-injection by VRE sources c) Limited flexibility from hydropower stations and pumped storage plants due to high inflows and high reservoir levels d) Inadequate flexibility of intra-state thermal generating stations and under- drawl e) Lack of DOWN reserves at the interstate level f) Inadequate liquidity in DAM/RTM, resulting in the states committing more units.

Frequency Profile:

3. On 04th August 2024, the frequency of the Indian grid exceeded the upper limit of the IEGC band (50.05 Hz) for a significant portion of the day. Starting at around 11:00 hrs., the frequency rose above 50.05 Hz and remained elevated until approximately 15:30 hrs. The maximum frequency recorded during the day was 50.39 Hz at 12:02:30 hrs. The frequency profile for 04th August 2024 is as under:

4. On 11th August 2024, the All-India power system experienced notable deviations in its frequency profile, with the system frequency consistently remaining above the Indian Electricity Grid Code ( IEGC ) permissible upper band of 50.05 Hz for a considerable portion of the day. The frequency remained high between 09:30 hrs and 15:00 hrs, barring a few minutes during this period.

The maximum instantaneous frequency recorded was 50.329 Hz at 13:44:50 hrs. Over the course of the day, the average frequency was measured at 50.043 Hz, which, although close to the nominal value of 50 Hz, highlights some deviation from the ideal frequency range. The frequency profile for 11th August 2024 is as under:

5. On 25th August 2024, the All-India power system experienced deviations in its frequency profile, with the system frequency staying above the Indian Electricity Grid Code ( IEGC ) permissible upper band of 50.05 Hz for an extended period. The frequency remained above the IEGC band from approximately 08:30 hrs to 16:00 hrs, except for a few short intervals. The maximum instantaneous frequency recorded during the day was 50.377 Hz at 13:07:50 hrs, and the average frequency for the entire day was 50.065 Hz, which, while close to the nominal 50 Hz, still reflected deviations from the ideal range. The frequency profile for 25th August 2024 is as under:

6. Grid-India, in its report, has suggested the following measures for enhancing flexibility in grid operations:

a) Reduction in a minimum turn down level of intrastate thermal stations as per CEA regulations

b) Reduction in a minimum turn down level to 40% of MCR

c) Two shift operation of selected thermal units with high energy charge rate

d) Incentivise flexible operation by notification of compensation for part load operation and start/stops

e) Implementation of resource adequacy framework

f) Increase the capacity of long duration storage

g) Power market reforms - reduce fragmentation of the market, raise the market cap, negative pricing

h) Frequency response from renewable energy sources

i) Curtailment of renewable energy generation as a last resort during sustained high-frequency Analysis and Decision

7. CERC

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top