HIGH COURT OF DELHI
MMTC LIMITED & ANR. – Appellant
Versus
OIL & NATURAL GAS CORPORATION LTD. – Respondent
OMP-330_2002
OMP330/2002
Page 1
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
OMP No.330/2002
5th February, 2010
MMTC LIMITED & ANR.
...Petitioners
Through:
Mr. Rohit Puri and Ms. Zurrat Zamal
Kaur, Advocates.
VERSUS
OIL & NATURAL GAS CORPORATION LTD.
....Respondent.
Through: Mr. Subhash Oberoi, Advocate
CORAM:
HON’BLE MR. JUSTICE VALMIKI J.MEHTA
1.Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3.Whether the judgment should be reported in the Digest?
%
JUDGMENT (ORAL)
VALMIKI J.MEHTA, J
1. By these objections under Section 34 of the Arbitration and Conciliation
Act, 1996, the petitioners challenge the Award dated 28.5.2002 of the sole
Arbitrator. The Award decides the dispute of the entitlement of damages of the
respondent on account of the petitioners having failed to supply the contracted
goods viz Sodium Carboxy Methyl Cellulose CMC(LVG) within the agreed
delivery schedule. The facts of the case are that two supply orders were placed
by the respondent on the petitioner No.2 M/s Kalpana Chemicals Limited.
2010:DHC:698
OMP330/2002
Page 2
Petitioner No.2 M/s Kalpana Chemicals thereafter assigned the contract to
petitioner no.1. Reference to the petitioners in this judgment therefore includes
reference as per the context to either or both the petitioner no.1 MMTC and
petitioner no.2 M/s Kalpana Chemicals Ltd.
2. The first supply order was for 200 metric tones(MT) dated 15.01.1993 as
per which the supply was to be made by 15.11.1993 and the second supply
order for 50 metric tones was dated 3.2.1993 for supply by 1.4.1994. The
admitted facts are that the petitioner failed to supply the contracted goods to the
respondent within the delivery period under the contract and consequently, the
respondent cancelled the contract on 27.10.1994. As a result of cancellation of
the contract, the respondent, on 23.5.1995, purchased at the risk and cost of the
petitioner, contracted goods, and thereafter instituted arbitration proceedings for
recovery of the higher cost paid for purchase of the contracted goods. The
respondent after encashing the bank guarantee of Rs.2,68,662/-, claimed the
balance amount with respect to the first contract at Rs.11,92,728.35 and with
respect to the second contract at Rs.3,77,817.50. As regards the aspect of
cancellation of the contract and subsequent risk purchase, certain dates and
additional facts are relevant and have to be noted. When the respondent wrote
its letters/telexes dated 27.10.1993 and 27.11.1993 to supply the balance 220
MTs, out of the total contracted quantity of 250 MTs, MMTC asked for
extension of the delivery period upto December 1994, but respondent wanted
the supply to be completed in three months and therefore refused to extend the
2010:DHC:698
OMP330/2002
Page 3
delivery period and cancelled the contract vide its letter dated 27.10.1994. The
actual risk purchase was however only made on 23.5.1995 i.e. well after
December 1994, the month/period to which the petitioners had asked for
extension of time.
3. Before the Arbitrator, the petitioner raised various disputes with regard to
the fact that it was not guilty of breach of contract because of force majeure
conditions and other issues. The Arbitrator has arrived at a finding of fact that
the petitioner was in fact guilty of breach of contract and the respondent was
entitled to terminate the contract. This part of the Award, assuming that there
could not have been extension upto December 1994, could not in any manner be
challenged by the counsel for the petitioner because such finding has not been
shown to me to be in any manner illegal or beyond the provisions of the
Contract or perverse.
4. The issue however which came up during the course of hearing of this
petition was whether there could be an Award for actual damages when the
contract in question