HIGH COURT OF DELHI
NORTH MUNICIPAL CORPORATION OF DELHI – Appellant
Versus
M/S HARCHAN DASS GUPTA CONST. PVT. LTD. – Respondent
OMP-114_2013
O.M.P.114/2013 Page 1 of 17
$~58
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+
O.M.P. 114/2013
%
Judgement Reserved on: 11th August, 2014
Judgement pronounced on: 25th August, 2014
NORTH MUNICIPAL CORPORATION OF DELHI
..... Petitioner
Through:
Ms.Shobhaa Gupta, Adv.
versus
M/S HARCHAN DASS GUPTA CONST. PVT. LTD.
..... Respondent
Through:
Mr.Virender Kumar Sharma,
adv.
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT
I.A.2285/2013 (for delay)
1. The present petition has been filed by the petitioner
challenging the award dated 19.9.2012. Along with the said petition,
the petitioner has also filed an application for condonation of delay in
refiling the petition. It is submitted in the said application that
petition was filed on 9.11.2012 which was returned with objection on
2014:DHC:4144
O.M.P.114/2013 Page 2 of 17
16.11.2012. Since then the petition has been under objection time
and again with different objections including for retyping of a large
number of annexures and all the objections were diligently removed
and the petition was refiled on 15.01.2013. A fresh objection
regarding the format of the petition was raised by the registry on
18.1.2013 which has also been removed. It is submitted that the
petition was delayed by approximately 48 days. It is submitted that
the delay in refiling was neither intentional nor deliberate but due to
reasons mentioned above.
2. The application is contested by the respondent who was issued
notice of this application. It is submitted that the petition was filed
on 9.11.2012. Thereafter it was admittedly refiled on 15.1.2013 and
thus there was a delay of two months. It is an admitted fact that there
is a delay of 60 days in refiling the petition and not 48 days as
contended. It is further submitted that even after 18.1.2013 the
refiling has been delayed by more than two weeks as is apparent from
the date of attestation of the affidavit. It is denied that the delay in
refiling was neither intentional nor deliberate. It is submitted that no
2014:DHC:4144
O.M.P.114/2013 Page 3 of 17
justification has been shown in delay in refiling and it is prayed that
the application as well as the petition be dismissed being barred by
limitation.
3. I have heard the arguments and have considered all the
contentions of the learned counsels for the parties.
4. In this case the award is dated 19.9.2012. The petition was
first filed on 9.11.2012. The period of limitation prescribed for filing
petition under Section 34 of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as ‘the Act’) is 90 days. The proviso to
the said section provides that the period of filing of petition under
Section 34 can be extended upto a further period of 30 days, if the
court is satisfied that the applicant was prevented by sufficient cause
from making the application within the said period of three months.
The Supreme Court in the case (2001) 8 SCC 470 titled as Union of
India vs. Popular Construction Co. has clearly held as under :
2014:DHC:4144
O.M.P.114/2013 Page 4 of 17
5. It therefore is a settled principle of law that provisions of
Section 5 of the Limitation Act are not applicable to the petition filed
under Section 34 of the Act, while calculating the period of limitation
for filing of the petition. There is no dispute to the fact that in the
present case, the petition was filed within 90 days of period of
limitation prescribed under Section 34 (3) of the Act. The award in
this case was passed on 19.9.2012 and the petition was filed on
9.11.2012. The petition so filed suffered with defects and registry
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.