HIGH COURT OF DELHI
VERSATILE COMMOTRADE PRIVATE LIMITED – Appellant
Versus
CHIRANJI LAL & ANR – Respondent
CS(COMM)-304/2016
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 09.02.2017
% Decided on: 17.03.2017
+
CS(COMM) 304/2016
VERSATILE COMMOTRADE PRIVATE LIMITED ..... Plaintiff
Through: Mr. Ratan Kumar Singh,
Mr. Nikhilesh Krishnan, Mr Nishank
Tyagi and Mr Abhishek Iyer,
Advocates
versus
CHIRANJI LAL & ANR
..... Defendants
Through: Mr Sunil Dalal and Mr Ashish
Sharma, Advocates
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT
IA No.23676/2015 (moved by defendants under Order XXXVII Rule 3
(7) CPC r/w S.151 CPC)
1.
The present application of the defendants under Order XXXVII Rule
3 (7) of Civil Procedure Code (CPC) relates to grant of leave to defend the
present suit, which has been filed by the plaintiff under Order XXXVII CPC
for recovery of a sum of `1,03,54,000/- along with interest at the rate of
18% per annum with effect from 02.11.2013 till actual payment. It is
submitted by the plaintiff that they are dealing in the business of real estate
and were interested in purchasing land in revenue estate of Village Surhera,
2017:DHC:1590
Tehsil Najafgarh, New Delhi. Defendants approached them in first weeks of
April, 2013 and offered to sell their agricultural land, the detail of which is
as under:
(These properties shall be hereinafter referred to as “suit property”)
It is further contended by the plaintiff that since they wanted to
purchase land in that area, they agreed to purchase the suit property and paid
a token amount of `80,54,000/- (vide Cheque no. 403870 dated 23rd April
2013 for a sum of `40,27,000/- in favour of defendant no. 1 and another
cheque no. 403871 dated 23rd April 2013 for `40,27,000/- in favour of
defendant no.2). The defendants accepted the said token amount and
promised to execute agreement to sell the suit property. However, they
started delaying the execution of the agreement to sell. After much
2017:DHC:1590
persuasion, the agreement to sell was executed on 18.07.2013 for total sale
consideration of `3,60,00,000/- per acre and also paid a sum of `11,50,000/-
to both the defendants and thus paid a total sum of `1,03,54,000/- to the
defendants towards the part sale consideration price and that the defendants
had also executed a receipt to this effect. In the agreement to sell, the
defendants had represented that there was no legal impediment in selling the
land. It is submitted that as per clause (1) of the agreement to sell it was
agreed that the plaintiff would pay the balance sale consideration to the
defendants within 90 days from the date of execution of the agreement to
sell i.e. by 18.10.2013 subject to the defendants obtaining No Objection
Certificate (NOC) from the concerned authority 15 days before 18.10.2013.
It is submitted that the defendants, instead of obtaining NOC sent a notice
dated 20.07.2013 alleging that the sale deed was to be executed on
18.07.2013 and that defendants had come to the office of Sub Registrar on
18.07.2013 for execution of the sale deed after obtaining NOC from the
competent authority and that the sale would stand cancelled and the advance
money would stand forfeited if the plaintiff failed to pay the balance sale
consideration within 15 days from the date of receipt of the said notice. This
notice was duly replied by the plaintiff on 14.08.2013 whereby the plaintiff
2017:DHC:1590
had denied the contents of the notice and insisted that the balance
consideration amount was payable by plaintiff only on furnishing the NOC
to the defendants 15 days prior to the date of execution of the sale deed with
defendants had failed to furnish. The plaintiff also disputed the contentions
of the defendants in notice dated 20.07.2013 that agreement to sale was
executed on 18.04.2013. The plaintiff further contends that the conduct of
the defendants shows that they were not interested
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.