SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

HIGH COURT OF DELHI
BHARAT HEAVY ELECTRICALS LIMITED – Appellant
Versus
EGYPTIAN ELECTRICITY TRANSMISSION COMPANY & ORS – Respondent
CS(COMM)-675/2017



CS(COMM) 675/2017

Page 1

$~OS-6

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

%

+

CS(COMM) 675/2017

BHARAT HEAVY ELECTRICALS LIMITED..... Plaintiff

Through

Mr.Amit Sibal, Sr.Adv. with

Mr.Prashant Mehta, Ms.Vasundhara Bhardwaj and

Mr.Soham Kumar, Advs.

versus

EGYPTIAN ELECTRICITY TRANSMISSION COMPANY & ORS

..... Defendant

Through

None for D-1

Mr.Ravinder Sethi, Sr.Adv. with Mr.Ajay Monga,

Mr.Ateev

Mathur,

Mr.Amol

Sharma

and

Ms.Jagriti Ahuja, Advs.for D-2

Mr.Naresh Thanai, Mr.J.P.Singh, Ms.Khushboo

Singh and Mr.Tushar Sharma, Advs.for D-3

CORAM:

HON'BLE MR. JUSTICE JAYANT NATH

JAYANT NATH, J. (ORAL)

IA No.6074/2018

1.

This application is filed under Order 39 Rule 4 CPC by defendant

no.3 seeking to vacate the interim order passed by this court on 3.10.2017.

This court on 3.10.2017 passed an interim order directing the defendants to

maintain status quo regarding the bank guarantees. Defendants No.2 and 3

were also restrained from transmitting to defendant No.1 the funds of the

Bank Guarantee as noted in that order.

2.

The case of the applicant/defendant No.3 in the present application is

that defendant No.3 is a foreign entity formed and working in Egypt and it is

not amenable to the jurisdiction of this court. The grievance of the applicant

2018:DHC:7945

CS(COMM) 675/2017

Page 2

is that defendant No.2 is not releasing the amount of guarantees despite the

same being invoked by defendant No.3 in view of the interim order passed

in these proceedings. It is also pleaded that applicant/defendant No.3 has

filed its written statement without submitting to the jurisdiction of this court

and has filed the present application seeking vacation of the interim

injunction order dated 3.10.2017. It is pleaded that on the ex parte order

been granted to the plaintiff it was mandatory for the plaintiff to deliver to

the applicant a copy of the application for injunction together with copies of

affidavit, plaint and documents being relied upon by the plaintiff. Plaintiff

has failed to supply the same and has failed to comply with the mandatory

provision of Order 39 Rule 3 CPC.

3.

It is further pleaded that on 19.9.2017 defendant No.1 had made

demands on the bank guarantees issued by defendant No.3. Therefore,

defendant No.3 in turn made demands under the counter guarantees issued

by defendant No.2. vide swift message sent on 28.9.2017. The applicant was

it is pleaded obliged to discharge the guarantees issued by it by paying the

guaranteed amount to defendant No.1. Hence, it is pleaded that defendant

No.3/applicant released fund to defendant No.1 on 20.12.2017. Hence, the

present application.

4.

I have heard learned counsel for the parties. Learned counsel

appearing for the applicant has vehemently submitted that there is no non-

compliance of the provisions of Order 39 Rule 4 CPC and hence the interim

order ought to be vacated. He relies upon the judgments of the Supreme

Court in A.Venkatasubbiah Naidu vs. S.Chellappan and Others, (2000) 7

SCC 695 and; AGI Logistics Inc & Anr. vs. Sher Jang Bahadur & Anr.,

163(2009) DLT 137.

2018:DHC:7945

CS(COMM) 675/2017

Page 3

5.

Learned senior counsel appearing for the plaintiff has pointed out tht

immediately after the injunction order was passed by this court on

03.10.2017 they had by courier on 10.10.2017 in compliance of the

provisions of Order 39 Rule 3 CPC dispatched the complete paperbook to

defendant No.3. The paper book was received on 15.10.2017. Reliance is

placed on a legal opinion filed by defendant No.3 dated 18.10.2017 which

notes that the counsel were approached on 15.10.2017 for its opinion. This

document it is pleaded shows that on 15.10.2017 courier has been delivered

to the defendant No.3. He also relies upon judgments of the Division Bench

in Himalaya Drug Company vs. SBL Limited, 194 (2012)DLT 536and

judgments of this court in Nat Organic Chemicals Industries vs.

B.L.Industries, (1988