HIGH COURT OF DELHI
RAIL VIKAS NIGAM LTD. – Appellant
Versus
SIMPLEX INFRASTRUCTURES LTD – Respondent
O.M.P. (T) (COMM.)-28/2020
O.M.P(T)(COMM) 28/2020
Page 1 of 19
$~
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision:- 10.07.2020
+
O.M.P(T)(COMM) 28/2020
RAIL VIKAS NIGAM LTD.
.....Petitioner
Through:
Mr.Udit Seth, Adv.
versus
SIMPLEX INFRASTRUCTURES LTD
.....Respondent
Through:
Ms.Aanchal Mullick, & Mr.Pranjit
Bhattacharya, Advs.
CORAM:
HON'BLE MS. JUSTICE REKHA PALLI
REKHA PALLI, J (ORAL)
1.
The present petition preferred under Section 14 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the
Act’) seeks termination of the mandate of the 3-member Arbitral
Tribunal constituted to adjudicate the disputes between the parties, on
the ground that the Tribunal has willfully disregarded the ceiling
provided in Schedule IV of the Act while fixing its fee.
2.
The petitioner Rail Vikas Nigam Limited is a public sector
undertaking engaged in the business of railway construction projects
for the Indian Railways. On 27.09.2010, the petitioner issued an
Invitation to Bid for construction of Viaduct and related works for
4.748 km length in Joka-BBD Bag Corridor of Kolkata Metro Railway
Line, excluding the station areas from Ch.1250 to Ch.4128.00 between
Joka to Behala Chowrasta including Depot Approach at Joka. In
2020:DHC:2267
O.M.P(T)(COMM) 28/2020
Page 2 of 19
response thereto, the respondent submitted its bid which was accepted
by the petitioner by way of the letter dated 28.12.2010. Shortly
thereafter, on 28.01.2011, the parties executed a formal contract to
carry out the work, however the date of commencement was taken as
the date on which the Letter of Acceptance was issued, i.e.,
28.12.2010.
3.
Initially, as per the terms of the contract, the project was
earmarked for completion on 27.06.2013, but for various reasons the
original schedule could not be adhered to and the project completion
date kept being extended. Finally, on 20.11.2017, the respondent
completed the construction work as outlined in the Scope of Work in
the contract dated 28.01.2011. However, since the respondent claimed
that the petitioner’s failure to discharge its obligations under the
contract in a timely manner delayed the contract from a 30-month long
to an 84-month long project, it sought cost escalation from the
petitioner. Since repeated claims in this regard went unanswered, the
respondent invoked arbitration under Clause 17.3 of the General
Conditions of Contract (GCC) but the petitioner failed to appoint its
nominee arbitrator. Resultantly, the respondent approached this Court
by way of Arb. Pet. 519/2018 which was allowed on 11.12.2018. This
Court appointed Hon’ble Mr. Justice Swatanter Kumar (Retd.) as the
nominee arbitrator on behalf of the petitioner herein with a specific
direction that the fee of the learned arbitrator would be fixed as per
Schedule-IV appended to the Act.
4.
In its first sitting which took place on 15.01.2019, the learned
Tribunal recorded that its fee would be assessed as per Schedule IV to
2020:DHC:2267
O.M.P(T)(COMM) 28/2020
Page 3 of 19
the Act. The parties completed all pleadings thereafter and made part
payment towards fees. On 09.01.2020, in its 8th sitting, the Tribunal
extended the time for rendering an award by six months with the
consent of the parties, and after observing that only two installments of
Rs.5 lakh each had been paid towards arbitrators’ fee, directed the
parties to pay the outstanding dues which, in terms of Schedule IV to
the Act, was observed as Rs.49,87,500/-. Consequently, the parties
were granted four weeks’ time to pay the fee.
5.
Aggrieved by the fixation of fee, the petitioner preferred an
application before the learned Tribunal on 27.02.2020 averring that the
fee fixed exceeds the statutory ceiling limit of Rs.30,00,000/-
prescribed in Schedule IV of t