HIGH COURT OF DELHI
NORTH DELHI MUNICIPAL CORPORATION – Appellant
Versus
M/S DHINGRA CONSTRUCTION COMPANY – Respondent
CM(M)-136/2020
$~41
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 5th February, 2020
+
CM (M) 136/2020
NORTH DELHI MUNICIPAL CORPORATION ..... Petitioner
Through:
Ms.
Namrata
Mukim,
Standing
Counsel with Mr Manoj and Mr. R.
K. Sethi, AEs from Keshopuram Zone
in person. (M:9899106515)
versus
M/S DHINGRA CONSTRUCTION COMPANY ..... Respondent
Through:
Mr. S. K. Singh and Mr. Arunav
Tewari, Advocates. (M:7683051144)
CORAM:
JUSTICE PRATHIBA M. SINGH
Prathiba M. Singh, J. (Oral)
CM APPL. 4637/2020 (exemption)
1.
Allowed, subject to all just exceptions. Application is disposed of.
CM (M) 136/2020
2.
A suit for recovery was filed by M/s. Dhingra Construction Company-
Respondent/Plaintiff (hereinafter „Plaintiff‟) against North Delhi Municipal
Corporation (hereinafter „Corporation‟) as Defendant No.1 and the
Executive Engineer of the Corporation as Defendant No.2. It was pleaded
by the Corporation that due to change of panel of counsels etc. and various
other reasons the written statement on behalf of the Corporation was
delayed. However, the trial court, has vide the impugned order dated 24th
January 2020, refused to take the written statement on record.
3. Ld. counsel for the Corporation submits that the Trial Court has failed
2020:DHC:823
to consider that insofar as the Defendant No.2 was concerned, the service of
summons was effected only on 12th October, 2019. Accordingly, she
submits that the written statement was within time and ought to have been
taken on record.
4.
Summons were issued on 17th September, 2019. The Defendant No.1
was served on 23rd September, 2019 and the Defendant No.2 - Executive
Engineer was served on 12th October, 2019. The returnable date for the
summons was fixed as 24th January, 2020. On the said date, when the
written statement was tendered before the Court, the Court refused to take
the same on record on the ground that the written statement was beyond the
period of 120 days. Considering the fact, that summons were served upon
the Defendant No.2 i.e. the Executive Engineer of the Corporation, only on
12th October 2019, the written statement, which was tendered on 24th
January 2020, is directed to be filed on record subject to payment of
Rs.10,000/- as costs to be paid to the Plaintiff. The costs shall be paid on or
before the next date before the Trial Court i.e. 10th February, 2020, subject
to which the written statement shall be taken on record. Though this is a
commercial suit, the written statement is being directed to be taken on
record because the main Defendant i.e. Executive Engineer of the
Corporation, who had to file the written statement, was served on 12th
October, 2019 and the returnable date i.e. 24th January, 2020 when the
matter was listed, was within 120 days.
5. It is noticed in this case, that the summons in this suit were issued on
17th September, 2019. The said order reads as under:
“Present :-Ms. Shwenka Tripathi, Counsel for the
2020:DHC:823
Put up for further proceedings on 24.01.2020.”
6.
A perusal of the above order shows that the order issuing summons
does not give any timelines for filing of written statement, though the same
is contained in the Code of Civil Procedure.
7. It has been noticed that usually, in trial courts, in most matters, the
order issuing summons does not specify the time line for filing written
statement. The summons also does not specify the outer time limits. The
returnable date is then fixed beyond the 90 days/120 days period. The usual
method of filing in trial courts is to present the pleading on the date when
the matter is fixed. Thus, the returnable date plays a crucial role. Litigants
who receive the summons and/or the orders, usually are not aware of the
timelines and the mandatory nature of the 120 days’ period for filing of
written statement in the case of commercial suits, and in several cases, the
returnable date