HIGH COURT OF DELHI
PCL SUNCON (JV) – Appellant
Versus
NATIONAL HIGHWAY AUTHORITY OF INDIA – Respondent
O.M.P. (T) (COMM.)-80/2020
O.M.P. (T) (COMM.) 80/2020
Page 1 of 27
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 12.01.2021
+
O.M.P. (T) (COMM.) 80/2020
PCL SUNCON
.....Petitioner
Versus
NATIONAL HIGHWAY AUTHORITY
OF INDIA
.....Respondent
Advocates who appeared in this case:
For the Petitioner
: Mr Dr Amit George, Mr Swaroop George,
Mr Amol Acharya and Mr Rayadurgam
Bharat, Advocates.
For the Respondent
: Ms Madhu Sweta, Advocate.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1.
The petitioner – a Joint Venture constituted by Progressive
Construction Limited and SUNCON Construction Berhard, Malaysia
– has filed the present petition, inter alia, impugning an order dated
20.04.2020 passed by the two arbitrators terminating the arbitral
proceedings under Section 32(2)(c) of the Arbitration and Conciliation
Act, 1996 (hereinafter ‗the A&C Act‘).
2.
The present application is filed under Section 14(1)(a) read with
Section 15 of the A&C Act. The petitioner further prays for
2021:DHC:117
O.M.P. (T) (COMM.) 80/2020
Page 2 of 27
substitution of the Arbitrator by an independent arbitrator appointed
by this Court.
3.
The arbitral proceedings were terminated because the arbitrator
nominated by the petitioner had resigned and the petitioner had not
taken steps to nominate another arbitrator in his place. Consequently,
the arbitral proceedings could not proceed and the remaining two
arbitrators constituting the Arbitral Tribunal concluded that it was
impossible to continue the proceedings and, accordingly, terminated
the same. The petitioner claims that there was a communication gap
and the petitioner was not aware that the arbitrator appointed by it had
resigned. The Arbitral Tribunal had not issued any notice to the
petitioner in this regard prior to terminating the arbitral proceedings.
4.
The
respondent
(hereinafter
‗NHAI‘)
contests
the
maintainability of the present petition as well as contends that the
impugned order cannot be faulted.
5.
The aforesaid controversy arises in the following context.
6.
NHAI had invited bids for “Four laning and Strengthening of
No. GTRIP/5.” Pursuant to the said notice inviting tenders, the
petitioner submitted its bid on 15.12.2001 and it was opened on the
same day. The petitioner‘s bid was accepted and by a letter dated
23.02.2002, the petitioner was awarded the contract for an amount of
₹3,96,47,78,901/-. A formal agreement between the parties was
2021:DHC:117
O.M.P. (T) (COMM.) 80/2020
Page 3 of 27
executed on 28.03.2002. The works were divided into three sections.
The first section was to be completed within a period of eighteen
months from the date of commencement; the second section was to be
completed within a period of twenty four months from the date of
commencement; and the third section was to be completed within a
period of thirty six months from the date of commencement, that is, by
30.03.2005.
7.
The petitioner claims that certain disputes arose between the
parties in respect of the said contract. NHAI claims that the petitioner
did not complete the works within the stipulated time and therefore,
was liable to pay liquidated damages. The petitioner invoked the
arbitration
clause.
It
claimed
₹57,84,00,000/-
towards
overstay/overhead charges; ₹2,50,00,000 as refund of the liquidated
damages deducted by NHAI; and ₹40,04,000/- for rehabilitation of
Bridge 58/1. The petitioner also claimed waiver of liquidated
damages. In addition, the petitioner also claimed interest (pre-suit
pendente lite as well as future interest) as well as costs quantified at
₹10 lacs.
8.
The petitioner also filed a petition under Section 9 of the A&C
Act (O.M.P. 1019/2013) seeking certain measures of interim
protection. The said petition was disposed of by an order dated
09.01.2015 and the recovery of liquidated damages was stayed during
the arbi