HIGH COURT OF DELHI
RAJ SHARMA – Appellant
Versus
THE GENERAL MANAGER, N. RLY – Respondent
ARB.P.-763/2020
ARB.P. 763/2020
Page 1 of 5
$~2
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
ARB.P. 763/2020
RAJ SHARMA
..... Petitioner
Through
Mr. Avinash Kumar Trivedi,
Adv.
versus
THE GENERAL MANAGER, N. RLY
..... Respondent
Through
Mr. Jagjit Singh, Sr. Standing
Counsel with Mr. Preet Singh
and Mr. Vipin Chaudhary,
Advs.
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
O R D E R(ORAL)
%
15.04.2021
(video-conferencing)
C. HARI SHANKAR. J.
3.
The substratum of the disputes is contained in paras (i) to (xii)
ARB.P. 763/2020
1.
The reply, to this petition, though stated to have been filed, is
not on record. However, Mr. Jagjit Singh, Sr. Standing Counsel for
the respondent, has addressed arguments in the absence of the reply.
2.
The petition merely seeks reference of the disputes between the
petitioner and the respondent to arbitration under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (“1996 Act”).
2021:DHC:1353
ARB.P. 763/2020
Page 2 of 5
of para 7 of the present petition. However, as there is no contest
regarding the arbitrability of the dispute, it is not felt necessary to
reproduce the said paragraphs.
4.
Clause 64 of the General Conditions of the Contract (GCC)
applicable to the contracts with the railways, provides for arbitration
as the mode of resolution of disputes. Sub clause (1)(i) to (1)(v) and
(3)(b) of Clause 64 of the GCC may be reproduced thus:
“64.(1): Demand For Arbitration:
64.(1)(i): In the event of any dispute or difference between
the parties hereto as to the construction or operation of this
contract, or the respective rights and liabilities of the parties
on any matter in question, dispute or difference on any
account or as to the withholding by the Railway of any
certificate to which the contractor may claim to be entitled to,
or if the Railway fails to make a decision within 120 days,
then and in any such case, but except in any of the "excepted
matters” referred to in Clause 63 of these Conditions, the
contractor, after 120 days but within 180 days of his
presenting his final claim on disputed matters shall demand in
writing that the dispute or difference be referred to
arbitration.
64.(1)(ii)(a) The demand for arbitration shall specify the
matters which are in question, or subject of the dispute or
difference as also the amount of claim item-wise. Only such
dispute or difference, in respect of which the demand has
been made, together with counter claims or set off, given by
the Railway, shall be referred to arbitration and other matters
shall not be included in the reference.
64.(1)(ii)(b) The parties may waive, off the applicability of
sub-section
12(5)
of
Arbitration
and
Conciliation(Amendment) Act 2015, if they agree for such
waiver, in writing, after dispute having arisen between them,
in the format given under Annexure XII of these conditions.
2021:DHC:1353
ARB.P. 763/2020
Page 3 of 5
64.(1)(iii)(a) The Arbitration proceedings shall be assumed to
have commenced from the day, a written and valid demand
for arbitration is received by the Railway.
64.(1)(iii)(b) The claimant shall submit his claim stating the
facts supporting the claims alongwith all the relevant
documents and the relief or remedy sought against each claim
within a period of 30 days from the date of appointment of
the Arbitral Tribunal.
64.(1)(iii)(c) The Railway shall submit its defence statement
and counter claim(s), if any, within a period of 60 days of
receipt of copy of claims from Tribunal thereafter, unless
otherwise extension has been granted by Tribunal.
64.(1)(iii)(d) Place of Arbitration: The place of arbitration
would be within the geographical limits of the Division of the
Railway