DELHI HIGH COURT
NTPC VIDYUT VYAPAR NIGAM LIMITED – Appellant
Versus
SYMPHONY VYAPAR PVT LTD & ANR. – Respondent
O.M.P. (COMM)-164/2021
O.M.P. (COMM.) 164/ 2021
Page 1 of 18
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 09.08.2021
+
O.M.P. (COMM.) 164/2021 & IA No. 5828/2021
NTPC VIDYUT VYAPAR NIGAM LIMITED ..... Petitioner
versus
SYMPHONY VYAPAR PRIVATE LIMITED
& ANR.
..... Respondents
Advocates who appeared in this case:
For the Petitioner
: Mr Rituraj Biswas and Mr Rituraj
Choudhary, Advocates.
For the Respondents : Ms Mamta Tiwari, Ms Swati Sinha, Ms
Taruna A. Prasad and Mr Aman Bhatnagar,
Advocates.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1.
NTPC Vidyut Vyapar Nigam Limited (hereinafter „NVVNL‟)
has filed the present petition under Section 34 of the Arbitration and
Conciliation Act, 1996 (hereinafter the „A&C Act‟) impugning an
arbitral award dated 20.11.2020 (hereinafter „the impugned award‟)
rendered by an Arbitral Tribunal comprising of Justice (Retired) V.N.
Khare, former Chief Justice of India, Mr Ambarish Dave and Justice
(Retired) D.P. Wadhwa, former Judge of the Supreme Court of India
as the Presiding Arbitrator.
2021:DHC:2399
O.M.P. (COMM.) 164/ 2021
Page 2 of 18
2.
The impugned award was rendered in the context of disputes
that had arisen between NVVNL and respondent no.1 (hereinafter
„Symphony‟) in connection with a Power Purchase Agreement
(hereinafter the „PPA‟) entered into between NVVNL and Symphony.
3.
Essentially, the dispute between NVVNL and Symphony are
centered around the question whether NVVNL is entitled to recover
liquidated damages from Symphony in terms of clause 4.6 of the PPA.
NVVNL claims that it is entitled to recover ₹2,87,77,000/- (Rupees
Two Crores, Eighty-Seven Lakhs, Seventy-Seven Thousand only) as
liquidated damages being 10% of the Performance Bank Guarantee
furnished by Symphony, as according to NVVNL, Symphony had
failed to commission the solar power plant for generating 10 MW
capacity on or before the Scheduled Commissioning Date.
4.
According to NVVNL, Symphony had commissioned 5 MW
capacity on or before 26.02.2013 (the Scheduled Commissioning
Date) and commissioned the balance 5 MW on 27.02.2013. NVVNL
claimed that it was thus, entitled to recover half of 20% of the
Performance Bank Guarantee in terms of Clause 4.6 of the PPA.
Symphony disputed the aforesaid claim as according to Symphony, it
had commissioned the Solar Power Generating project before the
Scheduled Commissioning Date. It claimed that it had completed and
installed 10 MW of solar power generating capacity on 21.02.2013.
5.
The Arbitral Tribunal held in favour of Symphony and accepted
its contention that it had completed and installed the solar power plant
2021:DHC:2399
O.M.P. (COMM.) 164/ 2021
Page 3 of 18
with 10 MW capacity on or before the Scheduled Commissioning
Date of 26.02.2013. Accordingly, the Tribunal held that NVVNL was
not entitled to recover any liquidated damages. The Arbitral Tribunal
further held, in any event, NVVNL could not recover damages under
clause 4.6 of the PPA without establishing that it had suffered any
loss.
6.
Accordingly,
the
Arbitral
Tribunal
directed
that
the
Performance Bank Guarantee furnished by Symphony be discharged.
It also awarded costs of ₹1,08,66,000/- (Rupees One Crore Eight Lacs
and Sixty-Six Thousand only) in favour of Symphony.
7.
It is contended on behalf of NVVNL that the impugned award is
patently erroneous as it is contrary to the terms of the PPA. It is
contended on behalf of NVVNL that the impugned award disregards
the Minutes of the Meeting of Commissioning Committee of
25.02.2013/26.02.2013 – which recorded that Symphony had
electrically connected only 7.04 MW capacity as on 25.02.2013 – and
therefore, the impugned award is patently illegal and is liable to be set
aside.
Factual Background
8.
The Government of India launched the Jawaharlal Nehru
National Solar Mission (hereinafter „JNNSM‟) with the obj
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.