HIGH COURT OF DELHI
DELHI DEVELOPMENT AUTHORITY – Appellant
Versus
SATYA PRAKASH AND BROS PVT. LTD. – Respondent
O.M.P. (COMM)-489/2020
O.M.P. (COMM) 489/2020 Page 1 of 15
$~4 (2020)
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 25th August, 2021
+
O.M.P. (COMM) 489/2020 & I.A. 8844/2020
DELHI DEVELOPMENT AUTHORITY
..... Petitioner
Through:
Ms. Kanika Singh, Advocate.
versus
SATYA PRAKASH AND BROS PVT. LTD.
..... Respondent
Through:
Mr. Aseem Mehrotra, Advocate.
CORAM:
HON'BLE MR. JUSTICE SANJEEV NARULA
JUDGMENT
[VIA VIDEO CONFERENCING]
SANJEEV NARULA, J. (Oral):
1. The present petition under Section 34 of the Arbitration and
Conciliation Act, 1996 [hereinafter, ‘the Act’] has been filed by the
Petitioner [hereinafter, ‘DDA’] seeking setting aside of the impugned
Arbitral Award dated 22nd April, 2020 [hereinafter,‘Award’] passed the
Sole Arbitrator, in so far as it awards the amount qua Claim No. 3 and
interest thereon under Claim No. 5 in favour of the Respondent herein –
M/s. Satya Prakash & Bros. Pvt. Ltd. (being the Claimant therein)
[hereinafter, ‘SPBPL’].
BRIEF FACTS
2. The facts giving rise to the present petition are summarized as
2021:DHC:2627
O.M.P. (COMM) 489/2020 Page 2 of 15
follows: -
2.1
SPBPL being the L-1 bidder, was awarded contract for work of
village Karala Mazari for part of alignment passing through Rohini”,
by DDA, under Agreement No. 03/EE/MPR1/DDA/2012-13 for a
value of Rs. 56,16,62,727/-. The stipulated commencement date was
14th January, 2013 and completion date was 13th April, 2014.
2.2
A separate Supplementary Agreement - No. 3A/EE/MPR-1/DDA/
2012-13 was also executed between the parties.
2.3
Agreement Item no. 4 of Bill of Quantities [hereinafter, ‘BOQ’]
pertained to construction for embankment by getting earth from “all
leads and lifts, transporting to site”. The tender estimate rate for the
same was fixed by DDA as Rs. 171.10/- [calculated taking the
transportation lead of 20 kms]; SPBPL quoted the rate of Rs. 234/-;
the same was accepted by DDA; it was applicable to any/ all
distances.
2.4
During the execution of the work SPBPL expressed inability to source
the material (earth) and requested DDA for helping/ arranging
procurement of earth for execution of work, as ‘earth’ was not
available in nearby areas, on account of ban imposed by the Supreme
Court on excavation of earth from cultivated land in NCR Delhi.
2021:DHC:2627
O.M.P. (COMM) 489/2020 Page 3 of 15
Acting upon the request of the SPBPL and in the interest of work,
DDA requested DSIIDC to allow earth to be procured from its site
which was at a distance of 8 kms. SPBPL was put to notice that it
would be treated as a substituted item relying on Clause 12 the
Agreement1 SPBPL, on the other hand, refuted DDA’s substitution of
the agreed ‘rates’ and contended and it had never agreed or consented
to the same. Disputes finally arose when, SPBPL received the final
bill from DDA and after scrutiny thereof, it was observed that
payments against some claims, were not included.
2.5
In the afore-noted background, when SPBPL invoked arbitration vide
letter dated 16th March, 2019, DDA appointed Mr. Sarvagya Kumar
Srivastava as the Sole Arbitrator. The arbitration proceedings have
now culminated into the Award dated 22nd April, 2020. DDA assails
the same qua following claims: -
Claim No. 3 – Rate of payment relating to embankment work under
the Agreement.
i.
The Claim No. 3, pertains to agreement Item No. 4 dealing with
construction of embankment with approved material (earth)
obtained from borrow pits with all lifts and leads. The exact
description contained therein reads as under: -
300-2 of MoRT&H specifications for Road & Bridge works – 2001”
1 Relevant portion of the Clause 12 of the Agreement is provided in the succeeding paras
2021:DHC:2627
O.M.P. (COMM) 489/2020