HIGH COURT OF DELHI
GAIL (INDIA) LIMITED – Appellant
Versus
M/S STERLING AND WILSON PRIVATE LIMITED – Respondent
O.M.P. (COMM)-298/2021
O.M.P. (COMM) 298/2021
Page 1 of 25
$~27
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 24thNovember, 2021
+
O.M.P. (COMM) 298/2021 & I.As. 12961-62/2021
GAIL (INDIA) LIMITED
... Petitioner
Through:
Ms.
Manmeet
Arora,
Ms.
Chand
Chopra and Mr. Tarang Gupta,
Advocates.
versus
M/S STERLING AND WILSON PRIVATE LIMITED ... Respondent
Through:
Mr. Sanjeev Kumar Tyagi, Advocate
with Mr. Jaydeep Ghosh, AR.
CORAM:
HON'BLE MR. JUSTICE SANJEEV NARULA
JUDGMENT
[VIA HYBRID MODE]
SANJEEV NARULA, J. (Oral):
1.
The present petition under Section 34 of the Arbitration and
Conciliation Act, 1996 [hereinafter, “the Act”] impugns the Arbitral Award
dated 12thJune, 2021 [hereinafter, “Award”], passed by the learned Sole
Arbitrator, whereby claims of the Respondent – M/s Sterling and Wilson
Private Limited [hereinafter, “SWL”] have been allowed in entirety against
the Petitioner – Gail (India) Limited [hereinafter, “GAIL”].
BRIEF FACTS
2.
Pursuant to a tender floated by GAIL for the work of ‘220 KV Outdoor
2021:DHC:3818
O.M.P. (COMM) 298/2021
Page 2 of 25
Pata, Uttar Pradesh’ [hereinafter, “Agreement”], SWL emerged as the
successful bidder. A Fax of Acceptance dated 14thDecember, 2011 was issued
conveying acceptance of the bid. The project was to be completed within 18
months from the date of issuance of Fax of Acceptance, i.e., by 13thJune,
2013.
3.
On 24thJanuary, 2012, a Detailed Letter of Acceptance [hereinafter,
“DLoA”] was issued to SWL. The DLoA, along with the Fax of Acceptance,
the Agreement, the Special Conditions of Contract [hereinafter, “SCC”], the
General Conditions of Contract [hereinafter, “GCC”] and the Bidding
Documents, governed the terms of the contract between the parties.
4.
As per Clause 16 of DLoA, the Resident Construction Manager/ Site-
in-charge of Engineers India Limited, was appointed as the Engineer-in-
Charge [hereinafter, “EIC”].
5.
The work under the Agreement was not completed within the scheduled
period of completion. It was only on 16thFebruary, 2016 that a Completion
Certificate was issued by Engineers India Limited. On 13thFebruary, 2016,
SWL submitted its final bill under the Agreement – which was disputed by
GAIL. The ‘Site-Clearance’ Certificate was issued by SWL on 16thFebruary,
2016 after finishing the project. Thereafter, SWL invoked arbitration vide
notice dated 16thApril, 2018, and disputes were referred to arbitration.
6.
SWL raised claims worth Rs. 2,42,22,993/- under following heads:
2021:DHC:3818
O.M.P. (COMM) 298/2021
Page 3 of 25
S. No.
CLAIM
SUM CLAIMED
1.
Release of retention money withheld by the Petitioner
on account of Price Reduction Scheme
Rs. 71,52,433/-
2.
Refund of recoveries carried out by the Petitioner from
the final bill submitted by the Respondent
Rs. 23,11,906/-
3.
Claim towards additional work done by the Respondent
(Electrical and Civil)
Rs. 28,56,175/- &
Rs. 12,45,272/-
4.
Compensation for extended stay
Rs. 54,00,000/-
5.
Interest
@15%
per
annum
from
01.03.2016
to
30.09.2018
Rs. 52,57,207/-
Total Sum Claimed (and awarded)
Rs. 2,42,22,993/-
7.
The learned Arbitrator framed issues, which are noted in paragraph 22
of the impugned Award, and on that basis, the afore-noted claims were
allowed in totality by way of the impugned Award.
CLAIMS AND ANALYSIS
8.
The submissions of counsel for both parties are separately dealt
hereinafter as per the heads of claims, which are as under:
9.
CLAIM NO. 1: RELEASE OF RETENTION MONEY WITHHELD ON
ACCOUNT OF PRICE REDUCTION SCHEME
9.1.
The learned Arbitrator has dealt with this Claim in Issues No. (i) & (ii)
of the Award under paragraphs no. 26 to 30.
9.2.
On this point, Ms. Manmeet Arora, counsel for GAIL, states as follows:
(i)
that the Award erroneously holds GAIL responsible for the delay in the
execution of the project – contrary to the documents placed on record
by both parties.
(ii)
The Arbitrator has erroneously and selectively relied upon the letter of
2021:DHC:3818
O.M.P. (COMM) 298/2021
Page 4 o