DELHI HIGH COURT
HINDUSTAN PETROLEUM CORPORATION LTD – Appellant
Versus
M/S DHAMPUR SUGAR MILLS LTD – Respondent
O.M.P. (COMM)-164/2020
ARBITRATION - AWARD - CHALLENGE - LIQUIDATED DAMAGES - TAKE OR PAY/SUPPLY OR PAY CLAUSE - BREACH OF CONTRACT - LOSS OR DAMAGE - PROOF - SECTION 74 OF THE INDIAN CONTRACT ACT, 1872 - SECTION 23(3) OF THE ARBITRATION AND CONCILIATION ACT, 1996 - AMENDMENT OF COUNTER CLAIM - DELAY - REJECTION - VALIDITY.The Court held that the Arbitral Tribunal erred in awarding damages under the 'Take or Pay/Supply or Pay' Clause without the claimant establishing the loss or damage suffered. The Court also held that the Arbitral Tribunal was justified in rejecting the claimant's application to amend the counter claim at a belated stage.The Court set aside the impugned award and disposed of the petitions accordingly.
Fact of the Case:
The parties entered into five agreements for the supply of ethanol. Disputes arose between the parties, and they were referred to arbitration. The Arbitral Tribunal awarded damages to the claimant under the 'Take or Pay/Supply or Pay' Clause and also awarded the amount claimed by the respondent on account of sales tax paid to the Sales Tax Authorities. Both parties challenged the award.
Finding of the Court:
1. The Arbitral Tribunal erred in awarding damages under the 'Take or Pay/Supply or Pay' Clause without the claimant establishing the loss or damage suffered.2. The Arbitral Tribunal was justified in rejecting the claimant's application to amend the counter claim at a belated stage.
Issues: 1. Whether the Arbitral Tribunal erred in awarding damages under the 'Take or Pay/Supply or Pay' Clause without the claimant establishing the loss or damage suffered?2. Whether the Arbitral Tribunal was justified in rejecting the claimant's application to amend the counter claim at a belated stage?
Ratio Decidendi: 1. Under Section 74 of the Indian Contract Act, 1872, a party can only recover reasonable compensation for breach of contract if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, only reasonable compensation can be awarded not exceeding the amount so stated.2. Section 23(3) of the Arbitration and Conciliation Act, 1996 allows a party to amend or supplement its claim or defense during the course of the arbitral proceedings, unless the arbitral tribunal considers it inappropriate to allow the amendment or supplement having regard to the delay in making it.
Final Decision: The Court set aside the impugned award and disposed of the petitions accordingly.
Key Points: - Liquidated damages can only be awarded if they represent a genuine pre-estimate of losses fixed by both parties and accepted by the court (!) (!) (!) . - An application to amend or supplement a claim or defense in arbitration may be allowed unless the arbitral tribunal finds the delay inappropriate, considering the circumstances (!) (!) (!) (!) (!) . - A party must establish loss or damage to enforce a take-or-pay/supply-or-pay clause; liquidated damages require proof of genuine loss or a reasonable pre-estimate (!) (!) (!) (!) (!) .
O.M.P. (COMM) 164/2020 & O.M.P. (COMM) 190/2020
Page 1 of 24
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 06.01.2022
+
O.M.P. (COMM) 164/2020 and IA No. 2870/2015
HINDUSTAN PETROLEUM
CORPORATION LTD
..... Petitioner
Versus
M/S DHAMPUR SUGAR MILLS LTD
..... Respondent
Advocates who appeared in this case:
For the Petitioner
: Mr Naveen Raheja and Ms Aditi
: Shastri, Advocates.
For the Respondent
:Mr. Prasenjit Keswani, Advocate
AND
+
O.M.P. (COMM) 190/2020
M/S DHAMPUR SUGAR MILLS LTD
..... Petitioner
versus
HINDUSTAN PETROLEUM CORPORATION
LTD
..... Respondent
Advocates who appeared in this case:
For the Petitioner
: Mr. Prasenjit Keswani, Adv.
For the Respondent
:Mr Naveen Raheja and Ms Aditi
: Shastri, Advocates.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/000069
O.M.P. (COMM) 164/2020 & O.M.P. (COMM) 190/2020
Page 2 of 24
VIBHU BAKHRU, J
Introduction
1.
The parties have filed these petitions under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereafter ‘theA&C Act’)
impugning an arbitral award dated 23.08.2012 (hereafter ‘the
impugned award’) rendered by an arbitral tribunal constituted by a
Sole Arbitrator (hereafter ‘the Arbitral Tribunal’).
2.
The impugned award was rendered in respect of the disputes that
had arisen between the parties in connection with the Agreements (five
in number), whereby Dhampur Sugar Mills Limited (hereafter ‘DSM’)
had agreed to supply ethanol to Hindustan Petroleum Corporation
Limited (hereafter ‘HPCL’).
3.
Undisputedly, HPCL was required to bear the sales tax on such
supplies of ethanol. However, it was entitled to mitigate the levy by
providing Form-C for the ethanol purchased from DSM. According to
DSM, HPCL failed and neglected to furnish the Form-Cs within the
time prescribed resulting in a sales tax assessment being framed on
DSM for enhanced sales tax and penalty. DSM claimed that the same
constituted a breach of the agreements in question and accordingly,
suspended the supply of ethanol under the four agreements in question
until the issue was resolved. HPCL treated the same as a default on the
part of DSM to supply the agreed quantity of ethanol and imposed a
penalty under the ‘Take or Pay/Supply or Pay’ Clause (clause 3 of the
agreements in question)
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/000069
O.M.P. (COMM) 164/2020 & O.M.P. (COMM) 190/2020
Page 3 of 24
4.
Thereafter, the parties entered into a fresh Agreement (hereafter
‘the Fifth Agreement’).
5.
HPCL sought to recover the penalty imposed under the ‘Take or
Pay/Supply or Pay’ Clauses of the first four agreements from the
consideration payable for the ethanol supplied under the Fifth
Agreement. DSM contends that the same was impermissible. It also
sought recovery of the sales tax paid on account of non-furnishing of
Form-C. In addition, it also claimed certain sums under the ‘Take or
Pay/Supply or Pay’ Clause under the agreements in question.
6.
The disputes between the parties were referred to arbitration,
which culminated in the impugned award.
7.
The Arbitral Tribunal awarded HPCL’s claim for penalty
imposed under the ‘Take or Pay/Supply or Pay’ Clause and also
awarded the amount claimed by DSM on account of sales tax paid to
the Sales Tax Authorities.
Factual Context
8.
On 07.02.2007, HPCL and DSM entered into an agreement for
supply of ethanol at various locations in Delhi. Thereafter, three similar
agreements were executed between the parties: (i) Agreement dated
28.06.2007 for supply of ethanol to HPCL’s locations in the State of
Punjab; (ii) Agreement dated 17.11.2007 for supply of ethanol to
HPCL’s locations in the State of Haryana; and (iii) Agreement dated
02.01.2008 for supply of ethanol to various locations in the Stat
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.