HIGH COURT OF DELHI
M/S SARADA CONSTRUCTION – Appellant
Versus
NATIONAL HIGHWAY AUTHORITY OF INDIA – Respondent
O.M.P. (COMM)-133/2021
Page 1 of 12
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 28.03.2022
+
O.M.P. (COMM.) 133/2021
M/S SARADA CONSTRUCTION
..... Petitioner
Versus
M/S NATIONAL HIGHWAY AUTHORITY
OF INDIA
..... Respondent
Advocates who appeared in this case:
For the Petitioner
:
Mr. Rajat Arora, Ms. Renu Bhandari
& Mr. Ekansh Bansal, Advs.
For the Respondent
:
Mr. Alok Kumar Jain, Adv.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1.
The petitioner has filed the present petition under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereafter ‘the A&C Act’)
impugning an Arbitral Award dated 17.12.2020 (hereafter ‘the
impugned Award’) rendered by an Arbitral Tribunal comprising of
three members (hereafter ‘the Arbitral Tribunal’).
2.
The petitioner assails the impugned award to the limited extent
that its claim for extra work done quantified at ₹3,66,44,746/- and the
cost of arbitral proceedings quantified at ₹9,68,000/-, has been denied.
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/001103
Page 2 of 12
3.
The respondent (hereafter ‘NHAI’) had issued an invitation to
tender for work of “Repair & Maintenance work of remaining stretches
1/2016)”
4.
The petitioner had submitted its bid pursuant to the aforesaid
invitation to tender and by a Letter of Acceptance dated 27.05.2016, the
petitioner was awarded the aforesaid contract at a value of
₹5,78,87,054.25/- (Rupees Five Crores Seventy Eight Lakhs Eighty
Seven Thousand Fifty Four and Twenty Five paise). Thereafter, on
20.06.2016, the parties had entered into an agreement (the Contract). In
terms of the Contract, the date of commencement of work was
20.06.2016 and the same was required to be completed within a period
of three months; that is, on or before 19.09.2016. The Defect Liability
Period was stipulated as twenty-four months from the date of the
completion of the works. The works were completed on 11.10.2016,
therefore, the Defect Liability Period would expire on 10.10.2018.
5.
The Arbitral Tribunal accepted NHAI’s contention that it had
pre-closed the Contract in respect of the stretch of the highway from
KM 51.00 to KM 52.400 with effect from 14.03.2017 and had informed
the petitioner regarding the same on 04.01.2018. Similarly, the Contract
in respect of some stretches of the highway were pre-closed with effect
from 27.07.2018 and some were pre-closed with effect from
14.10.2018. However, the petitioner disputes that the Defect Liability
Period was foreclosed and claims that the Defect Liability Period
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/001103
Page 3 of 12
Certificate dated 22.10.2018, issued by the Engineer does not mention
any pre-closure.
6.
NHAI, by a letter dated 16.01.2019, informed the petitioner that
the Bank Guarantee furnished by the petitioner for a sum of
₹57,88,710/- was encashed. NHAI appropriated a sum of ₹47,07,951/-
and deposited the balance amount of ₹10,80,759/- recovered by
encashment of the Bank Guarantee in the petitioner’s bank account.
The sum of ₹47,07,951/- retained / appropriated by NHAI comprised of
₹71,191/- as penalty for pre-closure of the Defect Liability Period and
₹46,36,760 as amount paid for execution of the balance works at the
risk and cost of the petitioner. NHAI claims that it had engaged the
Public Works Department for executing the repair work, which the
petitioner had failed to do during the Defect Liability Period, and had
incurred a cost of ₹46,36,760/-.
7.
The petitioner claims that the recovery of the aforesaid amount is
illegal as it had not committed any default in performance of its
obligation. The petitioner further claims that it had executed certain
additional works during the Defect Liability Period and is entitled for
payment fo