HIGH COURT OF DELHI
PINK CITY EXPRESSWAY PRIVATE LIMITED – Appellant
Versus
NATIONAL HIGHWAY AUTHORITY OF INDIA & ANR. – Respondent
O.M.P.(I) (COMM.)-166/2022



O.M.P.(I) (COMM.) 166/2022

Page 1

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

%

+

O.M.P.(I) (COMM.) 166/2022

PINK CITY EXPRESSWAY PRIVATE LIMITED

..... Petitioner

Through:

Mr. Amit Sibal, Sr. Adv. with

Mr. Suryadeep Singh, Mr. Sidhant

Dwibedi, Mr. Rishabh Sharma,

Mr. Vinay Tripathi, Mr. Darpan

Sachdeva, Mr. Rishahh Sharaia,

Ms. Radha R. Tarkar, Ms. Aishwaiya

Kumar and Mr. Aaron Shaw, Advs.

versus

NATIONAL HIGHWAY AUTHORITY OF INDIA & ANR.

..... Respondents

Through:

Mr. Parag Tripathi, Sr. Adv. with

Mr. Ankur Mittal, Mr. Abhay Gupta,

Mr. Yash Kapoor and Ms. Vishakha

Nagraj, Advs. for NHAI/R-1

Mr. Sandeep Sethi, Sr. Adv. with

Mr. Raunak Dhillon, Ms. Madhavi

Khanna and Ms. Ananya Dhar

Choudhury, Advs. for R-2

CORAM:

HON'BLE MR. JUSTICE V. KAMESWAR RAO

V. KAMESWAR RAO, J. (ORAL)

1.

The present petition has been filed by the petitioner with

the following prayers:-

This is a digitally signed Judgement.

NEUTRAL CITATION NO: 2022/DHC/002228

O.M.P.(I) (COMM.) 166/2022

Page 2

c) Pass such further order/orders as this Hon’ble Court may

case.”

2.

It is the case of the petitioner and so contended by Mr.

Amit Sibal, learned Senior Counsel appearing for Pink City

Expressway Private Limited (hereinafter referred to as „petitioner‟

and „concessionaire‟ interchangeably) that the petitioner and the

respondent NHAI entered into a Concession Agreement dated June

6, 2008 with regard to widening (six laning) of Gurgaon-Kotputli-

Jaipur section of National Highway No.8 from KM 42.70 to KM

273.00 (length of 225.60 km) in the State of Haryana and

Rajasthan („Project Highway‟, hereinafter) on Build Operate and

Transfer („BOT‟, for short) basis.

3.

The petitioner has completed approximately 96% of the

widening of the Project Highway. He states that this aspect has

been accepted by the respondent / NHAI. It was also agreed that

the concession period shall be extended till August 2023 for

recovering the deferred premium. In the month of September

2017, owing to shortage of funds and non completion of the

project, a One Time Fund Infusion Scheme („OTFIS‟, for short) of

₹354 Crore was allowed for the completion of the pending works.

This is a digitally signed Judgement.

NEUTRAL CITATION NO: 2022/DHC/002228

O.M.P.(I) (COMM.) 166/2022

Page 3

He stated, it was also agreed by the NHAI that the petitioner has in

no way defaulted in executing the above work. A Review

Committee of the lenders was constituted and the respondent

NHAI with the power to impose and approve sanctions in case of

default by the concessionaire / petitioner in getting the above

amounts released. According to him, as per Article 29 of the

Concession Agreement, the concession is deemed to have been

extended, if the actual traffic at the Project Highway has fallen

short of the specific target traffic (79,835 PCUs per day) on the

target date. The petitioner as well as the respondent NHAI have

conducted their respective traffic surveys and have reached the

conclusion that the actual traffic has fallen short of the target by

more than 2.5% on the target date thereby leading to deemed

extension as per Article 29.1.2 of the Concession Agreement. In

fact, he stated that actual traffic has fallen short by 14.87% as per

the survey conducted by the petitioner. Even as per the survey

conducted by the respondent NHAI, the actual traffic has fallen

short by 14.86% of the target traffic. The respondent NHAI wrote

to

an

Independent

Engineer

and

requested

appropriate

recommendation regarding modification in the concession period.

He stated that after thorough examination of both the

abovementioned traffic sampling survey studies, the Independent

Engineer on August 01, 2018 determined and recommended an

extension of the concession period by 28 months and 24 days i.e.,

from April 03, 2021 to August 26, 2023. Accordingly, the Project

Director, Jaipur, verified and reaffirmed the recommendation of