HIGH COURT OF DELHI
CONTAINER CORPORATION OF INDIA LTD – Appellant
Versus
M/S SHIVAKRITI INTERNATIONAL LTD & ANR. – Respondent
FAO (COMM)-90/2022
FAO (COMM) 90/2022
Page 1 of 16
$~1
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
FAO (COMM) 90/2022 and CM Nos. 27091/2022,
27092/2022 & 27093/2022
CONTAINER CORPORATION OF INDIA
LTD.
..... Appellant
Through:
Ms Divya Singh and Mr
Paritosh Budhiraja, Advocates.
versus
M/S SHIVAKRITI INTERNATIONAL LTD
& ANR.
..... Respondents
Through:
Mr Sanjeev Puri, Senior
Advocate with Mr Prateek
Mishra, Ms Moinmoi Chatterjee
and Ms Tweisha Mishra,
Advocates for R-1.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
HON'BLE MR. JUSTICE AMIT MAHAJAN
VIBHU BAKHRU, J. (ORAL)
1.
The appellant has filed the present appeal impugning an ex
parte order dated 12.03.2021 passed by the learned District Judge,
inter alia, directing that the status quo be maintained in respect of the
Performance
Bank Guarantee no. 3178120BG0000192 dated
21.08.2020
and
the
Security
Deposit
Bank
Guarantee
No.3178120BG0000272 dated 06.10.2020 (hereafter ‘the PBG’ and
‘SDBG’ respectively).
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002250
FAO (COMM) 90/2022
Page 2 of 16
2.
Respondent no.1 (M/s Shivakriti International Ltd. – hereafter
‘SIL’) filed a suit, inter alia, praying for a decree of permanent
injunction restraining the appellant (hereafter ‘Concor’) from
invoking and encashing the PBG and SDBG. SIL further sought a
decree of permanent injunction restraining respondent no.2 (State
Bank of India) from acting upon any letter received from Concor
demanding the invocation of the two bank guarantees in question.
3.
The case set up by SIL in its plaint is briefly stated as under:
3.1
Concor issued a Letter of Acceptance (LoA) dated 06.02.2017
awarding the work pertaining to Signalling and Telecommunication at
Khemli Station on Chittorgarh-Udaipur Section of Ajmer Division on
North Western Railway. SIL signed the said LoA on 01.03.2017. In
terms of the LoA work was to be commenced on or before the 15th day
of the issuance of the LoA.
3.2
On 04.03.2017, SIL furnished a Performance Bank Guarantee
issued by State Bank of India for a sum of ₹34,64,482/- being 5% of
the contract value. Thereafter, on 23.03.2017, Concor and SIL entered
into a formal contract. It was stipulated that the work would be
completed within a period of six months from the date of
commencement (that is, six months from the 15th day of issuance of
LoA). SIL claims that Concor had failed and neglected to perform its
obligations under the contract and consequently, the work could not be
completed within the stipulated period of time. The time for
completing the contract was extended and SIL was constrained to
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002250
FAO (COMM) 90/2022
Page 3 of 16
extend the term of the Performance Bank Guarantee. SIL has averred
in its plaint that despite all obstacles, it continued to perform its
obligations within the limited scope as available. However, it was
unable to perform substantial work due to alleged inaction on the part
of Concor. SIL set out various reasons resulting in delay in
completion of the said works including the delay for a period of
almost 6 months on the part of Concor in deciding the supervising
agency; design and drawings submitted to the Sr. DTSE Ajmer had
not yet been approved; and station building for signalling and
telecommunication need had not been handed over as yet. It claims
that in the circumstances, it sought a short closure of the contract in
question but did not receive any response to the request. It claims that
in order to avoid forfeiture of the security deposit and earnest money
deposit, SIL sought extension of the contract up to 31.03.2019.