HIGH COURT OF DELHI
BHARAT HEAVY ELECTRICALS LTD. – Appellant
Versus
RAM RAJ AND ORS. – Respondent
W.P.(C)-3689/2022
W.P.(C) 3689/2022 Page 1 of 10
IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment delivered on: July 04, 2022
+
W.P.(C) 3689/2022 & CM APPL. 12784/2022
BHARAT HEAVY ELECTRICALS LTD.
..... Petitioner
Through:
Mr. Raj Birbal, Sr. Adv. with
Ms.Raavi Birbal and Mr.A.K.Roy,
Advs.
versus
RAM RAJ AND ORS.
..... Respondents
Through:
Ms. Asha Jain Madan and
Mr. Mukesh Jain, Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
J U D G M E N T
V. KAMESWAR RAO, J
1.
This petition has been filed by the petitioner / Bharat Heavy Electricals Ltd.
(BHEL) with the following prayers:
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002407
W.P.(C) 3689/2022 Page 2 of 10
case.”
2.
In substance, the challenge in this petition is to an order dated November 18,
2020, of the Assistant Labour Commissioner (Central) Delhi (‘ALC’, for short), in
his capacity as Conciliation Officer and also to a notice dated August 16, 2021,
issued to the petitioner in I.D.No.116/2021, by the Presiding Officer, CGIT-Cum
Labour Court- II (‘Labour Court’, for short) in pursuance to reference being made
to the Labour Court for adjudication of the dispute under Section 2A of the
Industrial Disputes Act, 1947 (‘ID Act’, for short). The order dated November 18,
2020, reads as under:
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002407
W.P.(C) 3689/2022 Page 3 of 10
Dayal Upadhyay marg, New Delhi.”
3.
It is a conceded case, that pursuant to the aforesaid order, the respondents
herein have filed a claim petition before the Labour Court on which notice has
been issued on August 16, 2021.
4.
The submission of Mr. Raj Birbal, learned Senior Counsel appearing along
with Ms. Raavi Birbal, for the petitioner is that the ALC could not have issued the
order dated November 18, 2020, advising the respondents to approach the Labour
Court directly under Section 2A of the Industrial Disputes (Amendment) Act,
2010, rather the matter should have been sent to the appropriate government
regarding the failure of the conciliation proceedings with reasons and it was for the
appropriate government to apply its mind and exercise its power to refer the
dispute to the Labour Court or not. In other words, it is their submission that by
resorting to the impugned order dated November 18, 2020, the appropriate
Government has been denied the power to exercise its discretion for referring the
matter to the Labour Court.
5.
That apart, it is further stated that the claim is stale, as the respondents had
worked with a certain contractor till 2017, and also due to the fact that in the
absence of an employer-employee relationship, no remedy could have been availed
by the respondent Nos.1 to 4 against the petitioner. The only remedy, if any, they
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002407
W.P.(C) 3689/2022 Page 4 of 10
have is against their employer, i.e., the contractor. In support of their submission,
Mr. Birbal / Ms. Birbal have relied upon the judgments in the cases of National
Engineering Industries Ltd. v. State of Rajasthan, (2000) 1 SCC 371, Nedungadi
Bank Ltd. v. K.P. Madhavankutty, (2000) 2 SCC 455, and ITDC v. Delhi
Administration, 1982 LabIC 1309 Delhi.
6.
On the other hand, Ms. Asha Jain Madan, learned counsel for the
respondents would contest the submission made by Mr. Raj Birbal and Ms. Raavi
Birbal by stating that there is no illegality in the order passed by the ALC,
inasmuch as by the said order, the ALC has only referred the parties to the CGIT,
which remedy in any case, is available to the