DELHI HIGH COURT
M/S NTPC VIDYUT VYPAR NIGAM LTD – Appellant
Versus
M/S DDE RENEWABLE ENERGY PVT. LTD – Respondent
O.M.P. (COMM)-317/2020
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
O.M.P.(COMM.) 317/2020
M/S NTPC VIDYUT
VYAPAR NIGAM LTD.
..... Petitioner
versus
M/S DDE RENEWABLE ENERGY PVT. LTD. ..... Respondent
Advocates who appeared in this case:
For the Petitioner
: Mr. Bharat Sangal, Sr. Adv. with Mr. R R
Kumar & Ms. Babita Kushwaha, Advs.
For the Respondents
: Mr. Deepak Khurana, Mr. Vineet Tayal &
Ms. Nishtha Wadhwa, Advs.
AND
+
O.M.P. (COMM). 374/2020
DDE RENEWABLE ENERGY PVT. LTD.
……Petitioner
versus
NTPC VIDYUT
VYAPAR NIGAM LTD. ……Respondent
Advocates who appeared in this case:
For the Petitioner
: Mr. Deepak Khurana, Mr. Vineet Tayal &
Ms. Nishtha Wadhwa, Advs.
For the Respondents
: Mr. Bharat Sangal, Sr. Adv. with Mr. R R
Kumar & Ms. Babita Kushwaha, Advs
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002441
JUDGMENT
VIBHU BAKHRU, J
INTRODUCTION
1.
The parties have filed the present petitions under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C
Act’) impugning an arbitral award dated 21.10.2019 (hereinafter ‘the
impugned award’) delivered by an Arbitral Tribunal comprising of
Justice (Retd.) G.N. Ray, Justice (Retd.) Usha Mehra, and Justice
(Retd.) G.B. Patnaik as the Presiding Arbitrator (hereinafter ‘the
Arbitral Tribunal’).
2.
The impugned award was rendered in the context of disputes
that have arisen between the parties in connection with a Power
Purchase Agreement dated 10.01.2011(hereinafter ‘the Agreement’).
THE CONTROVERSY
3.
The controversy in the present petition relates to the question
whether there was any delay on the part of DDE Renewable Energy
Pvt.Ltd. (hereinafter ‘DDE’) in complying with its obligations under
the Agreement and whether it was liable to pay liquidated damages for
the said delay, if any. In addition, NTPC Vidyut Vyapar Nigam
Limited (hereinafter ‘NVVNL’) had also claimed compensation for
shortfall in supply of solar power, which was disputed by DDE.
4.
The Arbitral Tribunal found that there was a delay of one day in
commissioning the solar project and DDE was liable to pay liquidated
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002441
damages quantified at 20% of the aggregate amount of the
performance bank guarantees. The Arbitral Tribunal further found
that DDE was not liable to pay any compensation for any shortfall in
supply of energy.
5.
Both the parties are aggrieved by the finding of the Arbitral
Tribunal regarding the delay in commissioning of the solar power
project and the consequent decision regarding levy of liquidated
damages. According to NVVNL, the delay is in excess of one month
and DDE is liable to pay an additional 40% of the aggregate amount
of the Performance Bank Guarantees as liquidated damages.
According to DDE, there is no delay in commissioning the solar
project in question and therefore, it is also aggrieved by the impugned
award. In addition, NVVNL is aggrieved by the decision of the
Arbitral Tribunal in absolving DDE of any liability on account of
shortfall in supply of solar power. Thus, both the parties have assailed
the impugned award to the extent that they are aggrieved.
FACTUAL CONTEXT
6.
In the month of July 2010, the Ministry of New & Renewable
Energy, Government of India (hereinafter ‘MNRE’) issued certain
guidelines for the selection of new grid connected solar power
projects. NVVNL was selected as a nodal agency for arranging and
purchasing solar power from Solar Power Developers (hereinafter
‘SPD’ in singular and ‘SPDs’ in plural).
7.
On 18.08.2010, NVVNL issued a request for selection
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/002441
(hereafter ‘RFS’), which was followed by a request for proposal
(hereafter ‘RFP’) on 29.10.2010.
8.
Pursuant to the said RFP, DDE (a SPD) submitted its bid fo
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.