HIGH COURT OF DELHI
IJM GAYATRI JV – Appellant
Versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA – Respondent
FAO(OS) (COMM)-92/2020
Page 1 of 32
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 07.10.2022
+
FAO(OS) (COMM) 92/2020 & CM APPL. 4216/2021 & CM
APPL. 4217/2021
IJM GAYATRI JV
..... Appellant
versus
NATIONAL HIGHWAYS AUTHORITY OF
INDIA
..... Respondent
Advocates who appeared in this case:
For the Appellant
: Mr. Angad Mehta, Adv.
For the Respondent
: Mr. Manish K. Bishnoi and Mr. Nirmal
Parsad, Advs.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
HON'BLE MR JUSTICE AMIT MAHAJAN
JUDGMENT
VIBHU BAKHRU, J
1.
M/s IJM-Gayatri (JV) (hereinafter ‘IJM’) has filed the present
appeal under Section 37(1)(c) of the Arbitration and Conciliation Act
(hereinafter ‘the A&C Act’) impugning a judgement dated 12.05.2020
(hereinafter ‘the impugned judgement’) passed by the learned Single
Judge, whereby National Highway Authority of India’s (hereinafter
‘NHAI’) application under Section 34 of the A&C Act, seeking to set
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/004080
Page 2 of 32
aside an arbitral award dated 09.08.2017 (hereinafter ‘the impugned
award’), was partially allowed.
Factual Context
2.
NHAI issued a Notice Inviting Tender (NIT) for execution of the
work relating to “widening of 4/6 lanes and upgrading of existing 2 lane
AP-13”
(hereinafter ‘the Project’), on the terms and conditions stipulated
thereon. Pursuant to the said NIT, IJM submitted its bid for executing
the Project works. IJM’s bid was accepted by NHAI and by a Letter of
Acceptance dated 20.04.2001 (hereinafter ‘the LoA’), the contract for
implementation of the Project was awarded to IJM for a consideration
of ₹225,39,46,841/-.
3.
Subsequently, on 25.05.2001, the parties entered into a formal
agreement [being Agreement no. 0040 /NH- 5/GQ/GM (E-l) /2001]
(hereinafter ‘the Agreement’). In terms of the Agreement, the works
were to be completed within a period of thirty-one months from the
commencement date and the defect liability period was stipulated as
twelve months.
4.
Thereafter, on 29.05.2001, NHAI issued a notice to proceed with
the work, in accordance with Clause 41.1 of the Special Conditions of
Contract (hereinafter ‘theSCC’). In terms of the said notice, the
scheduled date of commencement of work was stipulated as 01.06.2001
and the scheduled date of completion was stipulated as 31.12.2003.
This is a digitally signed Judgement.
NEUTRAL CITATION NO: 2022/DHC/004080
Page 3 of 32
5.
The Agreement provided for sectional completion of the Project
and was divided into three sections, that are, Section A: Km 292.000 to
Km 300.000, Section B: Km 300.000 to Km 330.000 and Section C:
Km 330.000 to Km 357.979.000 and Km 291.000 to Km 292.000.
Admittedly, there were certain delays in execution of the Project works
and IJM sought Extension of Time for completion of the works on
successive occasions, which were approved by NHAI.
6.
IJM claimed that it had immediately commenced the works and
duly mobilised its resources, however, the sites/stretches were not
handed over properly and/or free of encumbrances and thus, there were
delays and interruptions in execution of the works on the part of NHAI.
NHAI had disputed the same and according to it, the delays were on the
part of IJM. The date of completion for each section was extended up
to 24.03.2006, 31.12.2005 and 24.03.2006 respectively.
7.
Thereafter, on 28.08.2007, IJM submitted the ‘Statement at
Completion’, in accordance with Clause 60.10 of the Conditions of
Particular Application (hereinafter ‘COPA’) to the Acting Resident
Engineer. The Acting Resident Engineer certified certain payments,
however, excluded some claims submitted by IJM with the ‘Statement
at Completion’.
8.
Thereafter, on 21.10.2008, NHAI issued a Defect Liability
Period Certificate (hereafter ‘DLC’). Pursuant to the issuance of the
DLC, on 27.02.2