HIGH COURT OF DELHI
NNS ONLINE PVT LTD – Appellant
Versus
GOVT. OF NCT DELHI AND ANOTHER – Respondent
W.P.(C)-7926/2022
Neutral Citation Number 2022/DHC/004657
$~9
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
RESERVED ON –2nd September, 2022
%
PRONOUNCED ON -2nd November 2022
+
W.P.(C) 7926/2022, CM APPL. 24158/2022, CM APPL. 32932/2022
& CM APPL. 35957/2022
NNS ONLINE PVT LTD.
..... Petitioner
Through:
Mr.Vidit
Garg
and
Ms.Shipra
Mishral, Advocates
versus
GOVT. OF NCT DELHI AND ANOTHER
..... Respondents
Through:
Mr.Sunil Kumar, Adv. for respondent
no.1 with Mr.Manish Kumar Thakur,
Inspecting Officer, Labour Deptt.,
GNCTD.
Respondent no.2 in person.
CORAM:
HON'BLE MR. JUSTICE DINESH KUMAR SHARMA
J U D G M E N T
DINESH KUMAR SHARMA,J :
1.
The present writ petition has been filed challenging the order dated
25.03.2022 passed by Learned Presiding Officer, Labour Court, Rouse
Avenue, New Delhi, vide which the Learned Labour Court partly
allowed the application of the Respondent workman (claimant therein)
under order XII Rule 6, CPC, in the petition bearing LIR No. 1260/19,
under Section 17 (2) of the Working Journalist and Other Newspaper
Digitally Signed
By:PALLAVI VERMA
Signing Date:04.11.2022
15:29:54
Signature Not Verified
Neutral Citation Number 2022/DHC/004657
Employees (Conditions of Service) and Misc. Provisions Act, 1955,
(W.J. Act) filed on behalf of the workman, seeking issuance of
Recovery Certificate against statutory dues and inter alia held that
there is no requirement of leading any evidence regarding the
relationship of employer and the employee.
2.
Following two issues were framed to be adjudicated and determined:
(i)
Whether employee - employer relationship exists between the
claimant Sh. Chandra Prakash Pandey S/o Late Sh. Satya Nath
Pandey (Age-44 years, Mobile No.9013121141) and the
respondents/ managements?
(ii)
And if so, claimant Sh. Chandra Prakash Pandey S/o late Sh.
Satya Nath Pandey is entitled to difference of arrears of wages
amounting Rs.84,97,158.76/- for the period from 01.01.2006 to
01.07.2018 as per Majithia Wage Board recommendation under
Working
Journalist
and
Other
newspaper
Employees(Conditions of Service) and Misc. Provisions Act,
1955, and if so, what directions are necessary in this regard?
3.
During the proceedings, respondent workman preferred an application
under Order XII, Rule 6, CPC seeking an order on admission qua the
management for issuance of recovery certificate as per the statement of
claim filed on behalf of the workman. Learned Labour Court vide the
Impugned Order has partly allowed the application of the respondent
workman under Order XII, Rule 6, CPC, only to the limited extent of
Digitally Signed
By:PALLAVI VERMA
Signing Date:04.11.2022
15:29:54
Signature Not Verified
Neutral Citation Number 2022/DHC/004657
the 1st issue and disallowed the same with respect to the 2nd issue and
inter alia held as under:
“10. Accordingly application is disposed of and decided to the
extent that there is no controversy remained to be adjudicated
on the issue of employee employer relationship between the
management and workman and no evidence is required to be
led. There is no admission by management on the issue of
dues as referred in para 9 of claim petition by the claimant
alleging that he is entitled to recover arrears as on 01.01.2006
to 01.07.2018amounting to Rs. 79,17,840.25 and dues from
January, 2008 to November, 2011 amounting to Rs.
5,79,358.51. Totalling Rs.84,97,158.76. Though there is
admission qua employee and employer relationship between
the parties but there is noun equivocal and unambiguous
admission on the part of management regarding arrears to
the tune of Rs. 84,97,158.76which is to be proved by leading
evidence by both the parties. In such circumstances, the
application in hand cannot be allowed in totality. It is made
clear that no evidence is required to be led on the issue of
employer employee relationship. Application is accordingly
disposed of.”
4.
Thus the main grievanc