HIGH COURT OF DELHI
HK TOLL ROAD PRIVATE LIMITED – Appellant
Versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA – Respondent
O.M.P.(I) (COMM.)-118/2022
OMP(I)(COMM) No.118/2022
Page 1 of 11
$~66
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
O.M.P.(I) (COMM.) 118/2022
HK TOLL ROAD PRIVATE LIMITED
..... Petitioner
Through:
Mr.
Salim
A.
Inamdar,
Mr.
Modassir Husain Khan & Mr.
Abhishek Thakral, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY
OF INDIA
.. Respondents
Through:
None.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
VIBHU BAKHRU, J. (ORAL)
IA No.5668/2022 (for exemption)
1.
Exemption is allowed, subject to all just exceptions.
2.
The application is disposed of.
O.M.P.(I) (COMM.) 118/2022
3.
The petitioner has filed the present petition under Section 9 of the
Arbitration & Conciliation Act, 1996 (hereafter the ‘A&C Act’), inter
alia, praying as under:
“a) Grant an injunction against the Respondent from
recovering any amount whatsoever for alleged
breach of contractual obligations in terms of letter
dated 08.10.2021 from the Escrow Account
bearing No. 1903201010137 of Canara Bank at
Prime Corporate Branch, Mumbai.
2022:DHC:1366
OMP(I)(COMM) No.118/2022
Page 2 of 11
b) Grant an injunction on the operation of the letter
dated 09.09.2021 issued by the Respondent and
the IE's letters dated 22.10.2021 and 02.02.2022,
directing the proposed levy and recovery of the
damages from the Petitioner.
c) Grant ex parte ad interim reliefs in terms of the
above.”
4.
The respondent (hereinafter ‘NHAI’) had invited proposals by
issuing a Request for Qualification (RFQ) for shortlisting the bidders
for “construction, operation and maintenance of NH-7 Six-laning of
under NHDP Phase-V on BOT (Toll) on DBFOT basis” (hereinafter
‘the Project’).
5.
On 13.05.2010, NHAI had accepted the bid of Reliance
Infrastructure Ltd. and instructed furnishing of the Bank Guarantee for
a sum of ₹52.60 crores. Thereafter, the petitioner company was
incorporated as a Special Purpose Vehicle for executing the Project.
6.
On 02.07.2010, the parties entered into the Concession
Agreement for executing the said Project.
7.
It is stated that the petitioner had completed the Project and on
05.04.2016, a Provisional Completion Certificate was issued by the
Independent Engineer. The Project was thereafter, placed in
commercial service.
8.
The petitioner indicates that there were some issues with regard
to collection of toll and carrying out the maintenance works. The
petitioner claims that it had notified NHAI about the occurrence of a
2022:DHC:1366
OMP(I)(COMM) No.118/2022
Page 3 of 11
force majeure event on account of the outbreak of Covid-19 and the
measures taken for combating the pandemic. The petitioner also
claimed certain reliefs on account of the said force majeure events.
9.
According to the respondent, the petitioner was required to carry
out certain rectification works and to maintain the highway. On
01.12.2020, the Independent Engineer issued a letter to the petitioner to
carry out certain rectification work in respect of certain defects, in terms
of Clause 17.8 of the Concession Agreement. Thereafter, on
16.12.2020, NHAI also issued a notice under Clause 17.9.1 of the
Concession Agreement requiring the petitioner to carry out certain
repair/remedial measures in respect to the stated defects, within a period
of fifteen days. According to the petitioner, it submitted a detailed work
programme and also complied with the said directions. However, it
apparent that there is a dispute in this regard because according to
NHAI, certain defects have not been remedied.
10.
On 05.08.2021, the Independent Engineer sent a letter to the
respondent estimating the damages at ₹10,24,42,009/-, on account of
breach on the part of the petitioner to comply