HIGH COURT OF DELHI
PINK CITY EXPRESSWAY PRIVATE LIMITED – Appellant
Versus
NATIONAL HIGHWAY AUTHORITY OF INDIA & ANR. – Respondent
O.M.P.(I) (COMM.)-166/2022
O.M.P.(I) (COMM.) 166/2022
Page 1
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
O.M.P.(I) (COMM.) 166/2022
PINK CITY EXPRESSWAY PRIVATE LIMITED
..... Petitioner
Through:
Mr. Amit Sibal, Sr. Adv. with
Mr. Suryadeep Singh, Mr. Sidhant
Dwibedi, Mr. Rishabh Sharma,
Mr. Vinay Tripathi, Mr. Darpan
Sachdeva, Mr. Rishahh Sharaia,
Ms. Radha R. Tarkar, Ms. Aishwaiya
Kumar and Mr. Aaron Shaw, Advs.
versus
NATIONAL HIGHWAY AUTHORITY OF INDIA & ANR.
..... Respondents
Through:
Mr. Parag Tripathi, Sr. Adv. with
Mr. Ankur Mittal, Mr. Abhay Gupta,
Mr. Yash Kapoor and Ms. Vishakha
Nagraj, Advs. for NHAI/R-1
Mr. Sandeep Sethi, Sr. Adv. with
Mr. Raunak Dhillon, Ms. Madhavi
Khanna and Ms. Ananya Dhar
Choudhury, Advs. for R-2
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
V. KAMESWAR RAO, J. (ORAL)
1.
The present petition has been filed by the petitioner with
the following prayers:-
2022:DHC:2228
O.M.P.(I) (COMM.) 166/2022
Page 2
c) Pass such further order/orders as this Hon’ble Court may
case.”
2.
It is the case of the petitioner and so contended by Mr.
Amit Sibal, learned Senior Counsel appearing for Pink City
Expressway Private Limited (hereinafter referred to as „petitioner‟
and „concessionaire‟ interchangeably) that the petitioner and the
respondent NHAI entered into a Concession Agreement dated June
6, 2008 with regard to widening (six laning) of Gurgaon-Kotputli-
Jaipur section of National Highway No.8 from KM 42.70 to KM
273.00 (length of 225.60 km) in the State of Haryana and
Rajasthan („Project Highway‟, hereinafter) on Build Operate and
Transfer („BOT‟, for short) basis.
3.
The petitioner has completed approximately 96% of the
widening of the Project Highway. He states that this aspect has
been accepted by the respondent / NHAI. It was also agreed that
the concession period shall be extended till August 2023 for
recovering the deferred premium. In the month of September
2017, owing to shortage of funds and non completion of the
project, a One Time Fund Infusion Scheme („OTFIS‟, for short) of
₹354 Crore was allowed for the completion of the pending works.
2022:DHC:2228
O.M.P.(I) (COMM.) 166/2022
Page 3
He stated, it was also agreed by the NHAI that the petitioner has in
no way defaulted in executing the above work. A Review
Committee of the lenders was constituted and the respondent
NHAI with the power to impose and approve sanctions in case of
default by the concessionaire / petitioner in getting the above
amounts released. According to him, as per Article 29 of the
Concession Agreement, the concession is deemed to have been
extended, if the actual traffic at the Project Highway has fallen
short of the specific target traffic (79,835 PCUs per day) on the
target date. The petitioner as well as the respondent NHAI have
conducted their respective traffic surveys and have reached the
conclusion that the actual traffic has fallen short of the target by
more than 2.5% on the target date thereby leading to deemed
extension as per Article 29.1.2 of the Concession Agreement. In
fact, he stated that actual traffic has fallen short by 14.87% as per
the survey conducted by the petitioner. Even as per the survey
conducted by the respondent NHAI, the actual traffic has fallen
short by 14.86% of the target traffic. The respondent NHAI wrote
to
an
Independent
Engineer
and
requested
appropriate
recommendation regarding modification in the concession period.
He stated that after thorough examination of both the
abovementioned traffic sampling survey studies, the Independent
Engineer on August 01, 2018 determined and recommended an
extension of the concession period by 28 months and 24 days i.e.,
from April 03, 2021 to August 26, 2023. Accordingly, the Project
Director, Jaipur, verified and reaffirmed the recommendation of
2022:DHC:2228
O.M.P.(I) (COMM.) 166/2022
Page 4
the Independent Engineer and also suggested exten