HIGH COURT OF DELHI
SRICO PROJECTS PVT. LTD. – Appellant
Versus
CENTRAL RAILSIDE WAREHOUSE CO. LTD. – Respondent
ARB.P.-1216/2021
ARB.P. 1216/2021
Page 1 of 11
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Reserved on: January 20, 2022
Pronounced on: January 28, 2022
+
ARB.P. 1216/2021
SRICO PROJECTS PVT. LTD.
..... Petitioner
Through:
Mr. Shoeb Alam, Ms.Fauzia
Shakil & Mr. Ujjwal Singh,
Advocates
Versus
CENTRAL RAILSIDE WAREHOUSE CO. LTD. .... Respondent
Through:
Mr. K. K. Tyagi & Mr.Iftekhar
Ahmad, Advocates
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
JUDGMENT
1.
The present Petition is preferred by the petitioner under Section 11
(5) r/w Section (6) of the Arbitration and Conciliation Act, 1996 seeking
appointment of sole Arbitrator in terms of Clause- 25 of Clauses of
Contract of the Agreement dated 16.11.2017 executed with respondent.
2.
Petitioner-M/s SRICO Projects Pvt. Ltd. is a company registered
under the Companies Act, 1956 and with MSME and respondent- Central
Railside Warehouse Co. Ltd., an Enterprise of the Government of India,
is also a company registered under the Companies Act, 1956.
2022:DHC:325
ARB.P. 1216/2021
Page 2 of 11
3.
According to petitioner, it has participated in the tender process
issued by the respondent on 05.05.2017 for construction of 20400 MTC
Warehouse along with ancillaries, internal roads, and electrical
installation with temperature control facility at Fatuha, Bihar, at an
estimated cost of Rs.12,91,46,503.19/- and was awarded the said work at
an estimate cost of Rs.22,08,40,520.45/- and for this purpose, an
Agreement was executed at New Delhi on 16.11.2017. In terms of the
contract, petitioner was required to furnish a security deposit of 5% of
the tendered value in terms of Clause 15(i) and performance
security/guarantee of 5% of the tendered value i.e. Rs.1,10,42,000/-. The
work was to commence within 10 days of allocation of work order and
was to be completed within 15 months thereof i.e. by 11.02.2019.
However, the date of completion of work was extended various times
and thereby, completion of project was extended to or before 30-06-
2020. Petitioner claims to have satisfactorily completed the project
before 30.06.2020 and after completing the necessary Defects Liability
Period of one year as per the agreement, the project site was handed over
to the respondent on 30.06.2021.
4.
According to petitioner, respondent vide letter dated 15.04.2021
2022:DHC:325
ARB.P. 1216/2021
Page 3 of 11
informed the petitioner that from the payable amount of the submitted
13thRA Bill dated 06.07.2021, a deduction of Rs.1,32,50,431.23/-
(Rs.1,56,35,308/- with 18% GST) would be done on account of alleged
delay in the completion of project. In reply to the aforesaid letter,
petitioner by its reply dated 01.06.2021 denied respondents attribution of
delay, liability and default on the petitioner and also requested for an
amicable resolution of the disputes.
5.
During the course of hearing, learned counsel for petitioner
submitted that delay in completion of the project occurred due to various
and frequent breaches of project, warranties, conditions, timelines, delay
in removal of obstruction on sites, multiple modifications at the end of
respondent and in fact, petitioner had suffered huge losses due to
repeated and prolonged delays.
6.
Further, petitioner vide its letter dated 22.10.2021 called upon the
Manging Director of the respondent-company for release of the amount
deducted from the RA bill of petitioner, which was not replied to.
Thereafter, vide notice dated 12.11.2021 petitioner invoked arbitration
and proposed name of Mr.Justice (Retd.) Dharnidhar Jha to act as sole
arbitrator. However, the Managing Director of respondent by
2022:DHC:325
ARB.P. 1216/2021
Page 4 of 11
communication dated 22.11.2021 appointed Sh. Ratnesh Kumar Bariar as
the Sole Arbitrator to adjudicate the disputes between the parties.
7.
Learned counsel for petitioner submitted that appointment of
Ratnesh Kumar Baria