HIGH COURT OF DELHI
HINDUSTAN CONSTRUCTION COMPANY LTD – Appellant
Versus
IRCON INTERNATIONAL LIMITED – Respondent
ARB.P.-521/2015
Arb.P.521/2015 & Arb.P.522/2015
Page 1 of 4
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Date of Decision: 23rd December, 2015
+
ARB.P. 521/2015
HINDUSTAN CONSTRUCTION COMPANY LTD. ..... Petitioner
Through:
Mr. Rajeev Nayar, Sr. Adv. with
Mr.Dhirendra Negi, Mr. Divyam
Agarwal and Mr. Saurabh Seth, Advs.
versus
IRCON INTERNATIONAL LIMITED
..... Respondent
Through:
Mr. Dinesh Agnani, Sr. Adv. with
Ms. Leena Tuteja and Mr. Ishaan
Chawla, Advs.
AND
+
ARB.P. 522/2015
HINDUSTAN CONSTRUCTION COMPANY LTD. ..... Petitioner
Through:
Mr. Rajeev Nayar, Sr. Adv. with
Mr.Dhirendra Negi, Mr. Divyam
Agarwal and Mr. Saurabh Seth, Advs.
versus
IRCON INTERNATIONAL LIMITED
..... Respondent
Through:
Mr. Dinesh Agnani, Sr. Adv. with
Ms. Leena Tuteja and Mr. Ishaan
Chawla, Advs.
CORAM:
HON'BLE MR. JUSTICE J.R. MIDHA
JUDGMENT
1.
The petitioner is seeking appointment of an arbitrator under Section
11(6) of the Arbitration and Conciliation Act, 1996.
Arb.P.521/2015 & Arb.P.522/2015
Page 2 of 4
2.
There are valid arbitration agreements between the parties contained
in clause 59.3 of the agreements dated 18th February, 2006. The petitioner
validly invoked the arbitration vide notices dated 31st July, 2015 to
adjudicate the disputes between the parties.
3.
Learned senior counsel for the respondent has opposed this petition as
premature on the ground that the agreements provide for conciliation
proceedings by a conciliator before reference of the same to the arbitrator. It
was submitted that the petitioner invoked the conciliation process but filed
this petition without waiting for the conclusion of the conciliation
proceedings and therefore, the petition was premature. It was submitted that
the sole conciliator was appointed on 28th May, 2014 and vide notice dated
29th May, 2014, the conciliator called upon both the parties to file their
claim/counter-claims. The petitioner did not file the claim before the
conciliator who issued a reminder dated 25th March, 2015. Vide letter dated
9th April, 2015, the petitioner sought further time to file the claim before the
conciliator. The petitioner filed the claim before the conciliator on 28th
April, 2015. The respondent vide letter dated 26th May, 2015 sought time to
respond to the petitioner’s claim. The respondent filed the response as well
as counter-claim before the conciliator on 14th August, 2015. In the
meantime, vide letter dated 22nd July, 2015, the petitioner notified that there
was failure of conciliation. The conciliator in the meantime vide letter dated
26th August, 2015 fixed the first hearing of the conciliation on 14th
September, 2015. However, the petitioner vide letter dated 9th September,
2015 refused to appear before the conciliator and took a stand that
conciliation proceedings stood terminated. The conciliator therefore
terminated the conciliation proceedings vide order dated 17th September,
2015. The respondent vide letter dated 26th October, 2015 proposed the
names of the arbitrators from the nominated panel of northern Railways to
Arb.P.521/2015 & Arb.P.522/2015
Page 3 of 4
the Petitioner. The petitioner vide letter dated 30th October 2015, opposed
the respondent’s communication on the ground that the respondent forfeited
its right in view of the filing of the present petition.
4.
Learned senior counsel for the petitioner urged at the time of the
hearing that the agreements between the parties provide for sixty days for
conclusion of the conciliation proceedings. Vide letter dated 22nd July,
2015, the petitioner intimated the conciliator that more than 80 days had
passed without any steps having been taken in respect of the conciliation and
therefore, in terms of the contract, it was treating the conciliation as having
failed. The petitioner thereafter invoked the arbitration on 31st July, 2015
calling upon the Managing Director of the respondent to provide a panel of
names from wh