HIGH COURT OF DELHI
M/S T.K. ENGINEERING CONSORTIUM PVT. LTD. – Appellant
Versus
THE DIRECTOR (PROJECTS) RITES LTD. & ANR. – Respondent
ARB.P.-553/2020
Page 1 of 29
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 08.03.2021
+
ARB.P. 553/2020
M/S T.K. ENGINEERING CONSORTIUM PVT.
LTD.
..... Petitioner
Versus
THE DIRECTOR (PROJECTS) RITES LTD.
& ANR.
..... Respondents
Advocates who appeared in this case:
For the Petitioner
: Mr Rituraj Biswas, Ms Sujaya
: Bardhan, Mr Rituraj Choudhary and
: Mr Mayan Prasad, Advocates.
For the Respondents
: Mr G. S. Chaturvedi and
: Mr Shrinkar Chaturvedi, Advocates
: for RITES Ltd.
: Mr Ripu Daman Bhardwaj, CGSC
: for R-3.
CORAM
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1.
The petitioner, T.K. Engineering Consortium Pvt. Ltd. (hereafter
‘TKE’), is a company incorporated under the Companies Act, 1956 and
is engaged in providing Road Construction and other Engineering
services.
Digitally Signed
By:DUSHYANT
RAWAL
Signature Not Verified
Page 2 of 29
2.
TKE has filed the present petition under Section 11 of the
Arbitration and Conciliation Act, 1996 (hereafter the ‘A&C Act’), inter
alia, praying that an arbitral tribunal be constituted to adjudicate
disputes that have arisen between the parties in relation to the Contract
Agreement dated 27.02.2017 for “Development of Integrated Check
Post at Dawki (Meghalaya) along Indo-Bangladesh Border”.
3.
RITES Ltd. (hereafter ‘RITES’) had issued a Notice Inviting
Tender (NIT) on 01.08.2016 for “Development of Integrated Check Post
at Dawki (Meghalaya) along Indo-Bangladesh Border”. TKE submitted
its bid pursuant to the aforesaid tender. The same was accepted and,
RITES issued a Letter of Award (LoA) dated 30.09.2016, on behalf of
respondent no.3 (Land Ports Authority of India), awarding the contract
to TKE. Thereafter, RITES also entered into the Contract Agreement
dated 27.02.2017 (hereafter ‘the Agreement’).
4.
TKE claims that the site in question was handed over on
18.11.2016. It immediately mobilized resources (men and machinery)
and commenced excavation work. TKE claims that the execution of the
works was hampered by RITES and/or for reasons attributable to it,
resulting in TKE suffering losses to the extent of ₹2,37,23,39,473/-. It
also claims that the work was stopped by the Border Guards of
Bangladesh (BGB) as it objected to any activity within forty metres of
the International Border. In addition, the forest department also objected
to setting up of the camp sites. There were also substantial delays on the
Digitally Signed
By:DUSHYANT
RAWAL
Signature Not Verified
Page 3 of 29
part of RITES as it did not provide the necessary drawings and fronts
within the stipulated time for carrying out the work.
5.
On 07.01.2019, RITES issued a notice under Clause 3(ii) of the
General Clauses of the Contract (GCC) of the Agreement, calling upon
TKE to expedite the work failing which it would terminate the
Agreement. TKE responded to the said notice by its letter dated
09.01.2019 pointing out the reasons for the delay in execution of the
works.
6.
Notwithstanding the above, RITES terminated the Agreement by
a letter dated 17.01.2019. TKE challenged the termination letter dated
17.01.2019 before the High Court of Meghalaya by filing a petition
under Article 226 of the Constitution of India, being W.P. (C) 10/2019:
Others. The said petition was dismissed by an order dated 09.09.2019.
Aggrieved by the same, TKE filed a Special Leave Petition – SLP
(Civil) No. 26816 of 2019 – in the Supreme Court of India. The Supreme
Court, disposed of the said Special Leave Petition, by an order dated
22.11.2019 observing that “it would be appropriate for the petitioner to
as it may be advised”. The Supreme Court also made it clear that the
observations made by the High Court, while disposing of the Writ
Petition, would not be taken in