HIGH COURT OF DELHI
GEA EGI CONTRACTING / ENGINEERING CO LTD – Appellant
Versus
BHARAT HEAVY ELECTRICALS LIMITED – Respondent
EX.P.-443/2014
THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment delivered on: 16.09.2016
+
EX.P. 443/2014
GEA EGI CONTRACTING / ENGINEERING
CO LTD
..... Decree Holder
versus
BHARAT HEAVY ELECTRICALS LIMITED ..... Judgment Debtor
Advocates who appeared in this case:
For the Decree Holder
: Mr Sandeep Sethi, Senior Advocate with
Mr Puneet Singh Bindra, Mr Aslam
Ahmed, Mr Babit Singh Jamwal, Mr
Rohan Kaushal, & Mr Sharad Kharra.
For the Judgment Debtor
: Mr Neeraj Kishan Kaul, Additional
Solicitor General with Mr Samar
Kachwaha, Ms Manvi Adlakha and
Mr Basudeb Biswas.
CORAM:-
HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
EA(OS) 713/2015
1.
GEA EGI Contracting Engineering Co. Ltd. (hereafter 'GEA'), a
company incorporated under the laws of Hungary and having its principal
office at Hungary, has filed the present petition to enforce an arbitration
award dated 21.08.2014 (hereafter 'the impugned award') rendered by an
Arbitral Tribunal in respect of the disputes between GEA and Bharat Heavy
Electricals Limited (BHEL), a Government company incorporated under the
laws of India. The seat of arbitration was in Zurich, Switzerland and the
arbitration was conducted in accordance with the UNCITRAL Rules.
2.
BHEL has filed the aforementioned application (being EA (OS)
713/2015) under Section 48 of the Arbitration and Conciliation Act, 1996
(hereafter 'the Act'), inter alia, objecting to the enforcement of the
impugned award principally for two reasons. First, that BHEL has instituted
a suit - Suit No. 878/2014 (hereafter 'Noida Suit') - before the Civil Judge,
Senior Division, Gautam Budh Nagar, inter alia, praying for a mandatory
injunction restraining GEA to enforce the compliance of the impugned
award; and second, that the impugned award is contrary to the public policy
of India as, according to BHEL, the performance of the contract between the
parties was rendered impossible because of civil war like situation in the
Syrian Arab Republic (Syria).
3.
Thus, the only controversy to be addressed is whether the impugned
award is enforceable under Part II of the Act as a decree of this Court?
4.
Briefly stated, the necessary facts relevant to address the aforesaid
controversy are as under:-
4.1
Public Establishment of Electricity for Generation and Transmission
(PEEGT) is the main shareholder of Tishreen Power Public Corporation
which in turn operates the Tishreen Power Plant. PEEGT and BHEL
entered into a contract on 29.10.2009 (hereafter 'the PEEGT Contract')
whereby BHEL undertook to design, manufacture, transport, erect and
commission necessary equipment for extension of the Tishreen Power Plant
by addition of two units of 200 MW each to the existing capacity of the
Tishreen Power Plant (hereafter ‘theTishreen Project’).
4.2
On 01.12.2010, BHEL entered into an agreement (hereafter 'the
Agreement') with GEA for supply and erection of Dry Cooling Heller
System (hereafter 'the Equipment') for the Tishreen Project. In terms of the
Agreement, GEA was to supply equipment, materials and spare parts, CIF
Syrian Port of entry/CIP other modes of transportation. GEA also agreed to
provide design/ data for erection and commissioning procedures; supervise
the erection and commissioning of the equipment as well as the performance
test procedures; completion of performance test; and training of operating
and maintenance personnel. BHEL was obliged to pay for the Equipment in
the manner as provided under the Agreement.
4.3
On 21.05.2012, BHEL requested GEA to defer dispatches of certain
material, which were required at the later stage of the Tishreen Project.
During the period, 23.05.2012 to 06.06.2012, GEA issued pre-shipment
notices indicating their readiness to dispatch certain equipment as
contracted.
4.4
Thereafter, on 13.06.2012, BHEL sent a letter requesting GEA to
“stop dispatches against the subject contract with immediate effect