HIGH COURT OF DELHI
DELHI DEVELOPMENT AUTHORITY – Appellant
Versus
SHIV KUMAR WASAL & CO – Respondent
O.M.P.-297/2014
O.M.P. Nos.215/2014 & 297/2014
Page 1 of 8
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
O.M.P. 215/2014
%
Date of Decision: 23rd December, 2015
SHIV KUMAR WASAL & CO
..... Petitioner
Through:
Mr. Sanjay Goswami, Adv.
versus
DELHI DEVELOPMENT AUTHORITY
..... Respondent
Through:
Mr. Shashank Garg, Mr.Zaid
Ali, Advs.
With
O.M.P. 297/2014
DELHI DEVELOPMENT AUTHORITY
..... Petitioner
Through:
Mr. Shashank Garg, Mr.Zaid
Ali, Advs.
versus
SHIV KUMAR WASAL & CO
..... Respondent
Through:
Mr. Sanjay Goswami, Adv.
CORAM:
HON'BLE MR. JUSTICE J.R. MIDHA
JUDGMENT
1.
The award dated 07th November, 2013 passed by the learned
arbitrator is under challenge by both the parties.
2.
Delhi Development Authority, hereinafter referred to as “DDA”
awarded a contract for construction of 672 MIG flats at Narela to M/s
Shiv Kumar Wassal & Company, hereinafter referred as to
“Contractor” on 21st August, 1990. The Contractor completed the
work on 22nd October, 1993 and submitted the final bill which was
paid by Delhi Development Authority on 21st August, 1998.
3.
On 03rd November, 1998, the Contractor raised twenty two
O.M.P. Nos.215/2014 & 297/2014
Page 2 of 8
claims on DDA. On 16th November, 1998, the Contractor invoked the
arbitration clause for appointment of an arbitrator under clause 25 of
the agreement for reference of twenty two claims for adjudication.
4.
On 05th April, 2000, DDA referred only nine claims to the
arbitrator. However, the competent authority of the DDA did not
refer the other claims on the ground that they were not covered in the
scope of the agreement.
5.
The Contractor filed an application before the arbitrator under
Section 23(3) of the Arbitration and Conciliation Act, 1996 for raising
additional thirteen claims. However, vide order dated 11th August,
2005, the arbitrator permitted the Contractor to raise nine claims in
addition to the earlier nine claims.
6.
In the meantime, there was change of the arbitrator. The new
arbitrator took the view that he would adjudicate only the nine claims
referred to him by the competent authority. The Contractor filed a
petition under Section 11(6) of the Arbitration and Conciliation Act
which was allowed and the remaining thirteen claims were referred by
this Court to arbitration. In the meantime, the learned arbitrator passed
an award dated 03rd October, 2006 with respect to the original nine
claims.
7.
The Contractor has challenged the award of the learned
arbitrator in O.M.P.266/2007 for non-consideration of the left out nine
claims whereas DDA challenged the award in O.M.P.76/2007 with
respect to the nine claims allowed by the learned arbitrator.
8.
On 19th November, 2012, both O.M.P. Nos. 266/2007 and
O.M.P. Nos.215/2014 & 297/2014
Page 3 of 8
76/2007 were disposed of by this Court. The objections of DDA were
dismissed except concessional modification of the award in respect of
one of the claims. However, this Court allowed O.M.P.266/2007 by
directing DDA to appoint an arbitrator to decide the nine left out
claims of the Contractor.
9.
Vide award dated 07th November, 2013, the new arbitrator
allowed four claims of the Contractor. Both the parties have
challenged the said award. The Contractor has challenged the award
on the limited ground that learned arbitrator has not awarded pre-suit
and pendente lite interest in respect of the nine claims under the first
award whereas DDA has challenged the four claims allowed by the
arbitrator.
10.
Claim No.1/5:
Item 3.3(ii) of the agreement provides for RCC works in the
staircase from second floor to third floor level. The design was later
altered by DDA and staircase of second and third floor level was
cancelled as a result of which the claimant had to use extra manpower
and scaffolding for doing the work on the roof. The Contractor
demanded Rs.1,69,000/- against which the arbitrator awarded
Rs.46,275/-. The relevant portion of the impugned aw