HIGH COURT OF DELHI
DIRECTORATE GENERAL OF HYDROCARBONS – Appellant
Versus
M/S AMBIENCE EXIM (P) LTD – Respondent
O.M.P.-475/2014
OMP 475-2014
Page 1 of 4
$~
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
+
O.M.P. 475/2014
%
Date of Decision: 23rd December, 2015
DIRECTORATE GENERAL OF HYDROCARBONS ..... Petitioner
Through:
Mr. Somiran Sharma and Mr. K.P.
Sasiprabhu, Advocates.
versus
M/S AMBIENCE EXIM (P) LTD
..... Respondent
Through:
Mr. D.N. Goburdhan and Mr. Prabal
Bagchi, Advocates.
CORAM:
HON'BLE MR. JUSTICE J.R. MIDHA
JUDGMENT
1.
The petitioner has challenged the award dated 03rd January, 2014
whereby the learned arbitrator awarded Rs.98,42,413.35 along with interest
and cost to the respondent.
2.
Vide lease agreement dated 02nd July, 2007, the respondent let out
property bearing No.C-139, Sector-63, Noida to the petitioner for a period of
three years. Vide letter dated 29th January, 2008, the respondent let out
additional space of 2298 sq. ft. to the petitioner. After the expiry of initial 36
months, the lease was extended for a period of further 11 months up to 30th
June, 2011. The petitioner vacated the subject premises on 31st August,
2011. 3.
On 8th April, 2008, the petitioner awarded annual maintenance
contract to the respondent for providing the services for operation and
maintenance of two DG sets, one lift, two AC units, fire alarm, and detection
OMP 475-2014
Page 2 of 4
systems, fire hydrants and main electrical panel room for a period of one
year w.e.f. 1st April, 2008 to 31st March, 2009. On completion of one year,
the petitioner awarded fresh annual maintenance contract to the respondent
on annual basis till the vacation of the premises. The petitioner paid
Rs.53,36,861/- to the respondent under the aforesaid annual maintenance
contracts for the period from 1st April, 2008 to 30th August, 2011. On 3rd
January, 2012, the petitioner for the first time raised an objection that the
annual maintenance contracts have been executed by the petitioner under a
mistake because the respondent was liable to provide maintenance under
clause 8 of the lease agreement dated 2nd July, 2007. The petitioner sought
refund of Rs.53,36,861/- from the respondent before the learned arbitrator.
4.
The learned arbitrator rejected the petitioner’s claim seeking refund of
Rs.53,36,861. Relevant portion of the award is reproduced here under:-
OMP 475-2014
Page 3 of 4
5.
Learned counsel for the petitioner submitted that the annual
maintenance contracts have been executed by the petitioner under a mistake
and therefore, the petitioner is not liable to pay the annual maintenance
contract amount to the respondent.
6.
Learned counsel for the respondent submitted that the petitioner
awarded the annual maintenance contract to the respondent on 8th April,
2008 for a period of one year and renewed the same year after year. Clause
8 of the lease agreement dated 2nd July, 2007 would not in any manner
invalidate the annual maintenance contracts. On the other hand, the annual
maintenance contracts would supersede clause 8 of the lease agreement
dated 2nd July, 2007. It was further submitted that the plea of “mistake” is
OMP 475-2014
Page 4 of 4
misconceived and in any case, the petitioner did not lead any evidence to
prove the mistake and thereafter, the arbitrator was justified in rejecting the
petitioner’s claim for refund and awarding balance annual maintenance
contract amount to the petitioner.
7.
On careful consideration of the rival contentions of the parties, this
Court is satisfied that there is no infirmity whatsoever in the finding of the
learned arbitrator. The petitioner raised a vague plea of “mistake” in
executing the annual maintenance contracts but did not lead any evidence
whatsoever to prove the same. In the absence of any such proof, the learned
arbitrator was justified in rejecting the same.
8.
No other contention was urged before this Court at the time of the
hearing. It may be recorded that vide order dated 6th May, 2014, this Court
has already dismissed the pet