HIGH COURT OF PATNA
The Chief Justice
M/s Bihar Home Developers and Builders – Appellant
Versus
Shri Narendra Prasad Gupta – Respondent
REQ. CASE/28/2020
IN THE HIGH COURT OF JUDICATURE AT PATNA
REQUEST CASE No.28 of 2020
======================================================
M/s Bihar Home Developers and Builders, through its authorised and
registered Partner Sh. Rajiv Ranjan Kumar, S/o Late Sh. Sundeshwar Roy,
aged about 51 years, having registered office at B-107, Beur City Armaan,
Beur, Patna, also at B-405, Western Mall, R.P.S. Mode, 4th Floor, Bailey Road,
Patna.
... ... Petitioner/s
Versus
Shri Narendra Prasad Gupta, S/o Late Ramdhani Shaw, Resident of Mohalla
Danapur, Cant Road, Gaadi Khana, P.O.- Thana Khagaul, Zila, Patna, Bihar.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s
:
Mr. Anand Mishra, Advocate
Mr. Sumit Kumar Jha, Advocate
For the Respondent/s
:
Mr. T.N. Maitin, Sr. Advocate
Mr. Sudhir Kumar Bijpuria, Advocate
======================================================
CORAM: HONOURABLE THE CHIEF JUSTICE
CAV JUDGMENT
Date : 07-07-2021
The sole issue that arises for consideration in the present
petition is whether the allegation of fraud alleged by the
respondent would render the arbitration clause in the agreement
dated 15th November 2016 null and void?
2. The facts are short and simple.
3. Sometime in November 2016, the petitioner, a
registered private firm, entered into an agreement with the
respondent to develop and construct a property near Danapur,
Patna District. Allegedly, the petitioner paid huge sums of money
to the respondent at that time. In furtherance of the agreement,
the petitioner constructed a boundary wall for developing the plot
Patna High Court REQ. CASE No.28 of 2020 dt.07-07-2021
2/18
and applied for necessary permissions and sanctions under the
relevant statutes. Certain disputes having arisen, the parties
reduced the terms afresh into writing, which agreement dated
15.11.2016 was also registered with the appropriate authority.
This agreement contains an arbitration clause 17, which stands
invoked by the petitioner seeking appointment of a sole
arbitrator, more so in the absence of any response to the notice
dated 23rd September 2019 requiring the respondent to do so.
Petitioner alleges the respondent to have concealed correct
information of ownership and pending litigation inter se co-
owners. Further, the respondent adopted an obstructionist
approach in executing the project and implementing the terms of
the agreement.
4. On the other hand, the respondent alleges fraud
perpetuated by the petitioner in the execution of the agreement.
The document was not allowed to be read over before signing.
Thus challenging its validity, the respondent initiated civil
proceedings to declare the agreement null and void. They also
initiated criminal proceedings on fraud falling within the purview
of Sections 468 and 417 of the Indian Penal Code.
5. In reliance of his submission, supporting the petitioner,
Sri Anand Mishra, learned counsel for the petitioner has referred
Patna High Court REQ. CASE No.28 of 2020 dt.07-07-2021
3/18
to and relied upon the decisions of the Hon’ble Apex Court in
Chloro Controls India Private Limited, (2013) 1 SCC 641; A.
Ayyasamy Versus A Paramasivam and others, (2016) 10 SCC
386; Rashid Raza Versus Sadaf Akhtar, (2019) 8 SCC 710;
and N. N. Global Mercantile Pvt. Ltd. Versus Indo Unique
Flame Ltd. and others, 2021 SCC Online SC 13.
6. Seeking rejection of the petition on the ground that the
agreement is null and void Sri T. N. Maitin, learned Senior
Advocate, appearing for the respondent seeks reliance upon the
decision of the Hon’ble Apex Court in A. Ayyasamy Versus A
Paramasivam and others, (2016) 10 SCC 386 (para 23, 24 &
25); Rashid Raza Versus Sadaf Akhtar, (2019) 8 SCC 710
(para 4); Afcons Infrastructure Limited and another Versus
Cherian Varkey Construction Company Private Limited and
others, (2010) 8 SCC 24 (