HIGH COURT OF PATNA
Mr. Justice Mohit Kumar Shah
Kashish Developers Limited – Appellant
Versus
The State – Respondent
CWJC/2797/2021
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No. 2797 of 2021
======================================================
……………Petitioner
Versus
... ... Respondent/s
2/10
======================================
Appearance :
For the Petitioner :
Mr. P.K. Shahi, Sr. Adv.
Mr. Ranjeet Kumar, Adv.
For the State
:
Mr. Manoj Kumar Ambastha, SC-26
===================================================
CORAM: HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH
ORAL JUDGMENT
Date : 01-09-2021
The only relief prayed for and pressed by the
Ld. Sr. Counsel for the petitioner in the present
case is for setting aside the office order dated
24.11.2020
whereby
and
whereunder
the
agreement bearing agreement no. 1 SBD 2019/20,
entered into between the petitioner and the
Respondent-Executive
Engineer,
Building
Construction Department, Building Division, Buxar,
has been rescinded.
2.
The brief facts of the case are that a NIT was
published
by
the
Building
Construction
Department, Bihar, for construction of Government
Engineering
College
at
Dumraon,
Buxar,
in
pursuance whereof, the petitioner and two others
3/10
had submitted their tender and ultimately, the
petitioner was declared as the successful bidder
and a work order dated 27.7.2017 was issued by
the Executive Engineer, Building Division, Buxar, in
favour of the petitioner, whereafter an agreement
was executed and 18 months time was fixed for
completion of the work. It has been contended by
the petitioner that since the construction site could
not be made available to the petitioner, a fresh
work order dated 14.8.2019 was issued in favour
of the petitioner and the stipulated time frame for
completion of work was fixed as 18 months,
whereafter
an
agreement
was
executed
on
01.10.2019. It is a matter of record that on
account of disturbance on the site, there being no
proper road to reach the site, structural drawing of
the project being not handed over to the petitioner
in time and on account of the lockdown due to
outbreak of Covid-19 Pandemic, the project in
question could not be completed within time.
Nonetheless, the Chief Engineer (South), Building
4/10
Construction Department, Bihar, Patna, vide letter
dated 6.11.2020, had directed the Executive
Engineer, Building Division, Buxar, to cancel the
agreement of the petitioner, whereafter the
Executive Engineer, Building Division, Buxar, by
the
impugned
order
dated
24.11.2020,
has
rescinded the agreement.
3. The short point raised by the learned Senior
Counsel, Sri P.K. Shahi, is that a bare perusal of
the impugned order dated 24.11.2020 would show
that the Executive Engineer, Building Division,
Buxar, has cancelled the agreement in question on
the direction of the Chief Engineer (South),
Building Construction Department, Bihar, Patna, as
contained
in
letter
dated
6.11.2020.
It
is
submitted that Clause 1 of the general conditions
of contract provides for execution of an agreement
between the competent authority on behalf of the
Governor of Bihar and the Contractor. Clause 2(iv)
thereof defines the Engineer-in-Charge to be the
5/10
Engineer Officer, who shall supervise and be the
in-charge of the work and who shall sign the
contract on behalf of the Governor of Bihar. Clause
3 and Clause 14 of the “Conditions of Contract”
stipulates the situation under which the contract
can be determined.
4.
The learned Senior Counsel for the petitioner
has further submitted that the agreement in
question has been entered into between the
petitioner and the Executive Engineer, Building
Division, Buxar, hence, the competent authority to
rescind / terminate the contract in question was /
is the Executive Engineer, Building Division, Buxar,
nonetheless, the competent authority under the
contract, who is authorized to terminate the
contract