HIGH COURT OF CHHATTISGARH
MR. SHAMSHER SINGH – Appellant
Versus
GENERAL MANAGER – Respondent
WPC 1012/2022
['BASANT KAIWARTYA', '', 'SHYAMTA PRASAD SANNAT', 'VINAY MIMI', 'B MADHAVA RAO', 'PANKAJ AGRAWAL', '', 'DR SUDEEP AGRAWAL', 'RUCHI AGRAWAL']
1
NAFR
HIGH COURT OF CHHATTISGARH, BILASPUR
WPC No. 1012 of 2022
Mr. Shamsher Singh S/o Mr. Vidhyanchal Singh Aged About 42 Years R/o
Main Road Jarhi Colony, P.O. Bhatgaon Colliery, District- Surajpur (C.G.)
Pin- 497235
---- Petitioner
Versus
General Manager Bhatgaon, Area, South Eastern Coalfields Limited, Po
Bhatgaon, District- Surajpur (C.G.) 497235
---- Respondent
(Cause-title taken from Case Information System)
For Petitioner
:
Mr. Abhishek Banjare, Advocate.
For Respondents
:
Dr. Sudeep Agrawal, Advocate.
Hon'ble Shri Arup Kumar Goswami, Chief Justice
Hon'ble Shri
Sanjay Agrawal
, Judge
Order on Board
Per
Arup Kumar Goswami, Chief Justice
01.12.2022
Heard Mr. Abhishek Banjare, learned counsel for the petitioner. Also
heard Dr. Sudeep Agrawal, learned counsel, appearing for the respondent.
2.
Pursuant to a Notice Inviting Tender (NIT) dated 24.08.2021 issued by
the respondent for work of temporary patch repairing work at coal
transportation road near Songara of Mahan sub area of Bhatgaon area, the
petitioner was awarded the work for a total value of Rs.10,19,520/- by an
order dated 24.09.2021.
3.
The order dated 24.09.2021 clearly stated that the petitioner should
commence work within a period of ten days of issuance of the letter or
2
handing over of the site, which ever is earlier and period of completion of
work shall be fifteen days. The site for project was handed over to the
petitioner on 01.10.2021 and therefore, the date of completion was to be
15.10.2021.
4.
On 23.11.2021, the Staff Officer (Civil) Bhatgaon Area of the
respondent issued a letter to the petitioner stating that the petitioner had
neither started the work nor had submitted the work programme despite
several requests being made in that regard. It was observed that the
petitioner was not interested to take up the work and blocked important
work. Accordingly, invoking Clause 6.1 of the General Terms and Conditions
of the NIT, which is not enclosed by the petitioner in this petition, it was
recorded as follows:
“If the contractor, without reasonable cause or valid
reasons, commits defaults in commencing the work withing
the aforesaid time limit, the company shall, without
prejudice to any other right or remedy, be at liberty, by
giving 15 day’s notice in writing to the contractor to
commence the work, falling which to rescind the Letter of
Acceptance of Tender / Work Order. The bidder(s) will be
banned for 02(two) years for being eligible to submit bids in
CIL and its subsidiaries with the approval of Tender
Acceptance Authority with intimation to all concerned and
online blocking of bidder shall be done on receipt of written
communication from the Tender inviting Authority by
3
application admin of CIL e-Procurement Portal.
In light of the above department has no option other than to
serve you 15 day’s notice in reference to above. This may
be treated as final 15- day’s notice”
5.
In the letter dated 25.11.2022, the petitioner indicated certain
difficulties faced by him but there is no denial of the fact that he had not
given the work programme as alleged in the letter dated 23.11.2021.
Subsequently, by an order dated 29.01.2022, the following action was
taken:
“i.
Cancellation of your bid against NIT No.GM/BHAT/
CVL/eTENDER/21-22/32 dt. 24.08.2021 and to rescind the
letter of acceptance of tender/Work Order.
ii.
Debarring from participation in Re-tender for the
above work.
Iii.
Forfeiture of EMD of Rs.30,586.00 deposited by
you for this work.
iv.
Debarring from participating in all future tenders of
SECL, Bhatgaon Area for a period of 24 (Month) from the
date of issue of this letter.”
6.
By filing this petition, the petitioner prays for the following reliefs:
“10.i
That this Hon’ble Court may kindly be pleased to
direct the concerned respondents to cancel the letter of
debarring him from work.
4
10.ii
That this Hon’ble Court