HIGH COURT OF CHHATTISGARH
DIPAK KUMAR SINGH BANAFAR – Appellant
Versus
THE COLLECTOR – Respondent
WPC 3381/2021
['BADRUDDIN KHAN', '', 'M L KAUSHIK', 'YOGESH CHANDRA SHARMA', 'A G']
HIGH COURT OF CHHATTISGARH, BILASPUR
WPC No. 3381 of 2021
Dipak Kumar Singh Banafar S/o Late Birbal Singh Banafar Aged About 41 Years R/o
Village- Jhirnapondi, Tahsil- Marwahi, District- Gaurela- Pendra- Marwahi,
Chhattisgarh
---- Petitioner
Versus
1. The Collector Gaurela- Pendra- Marwahi, District- - Gaurela- Pendra- Marwahi,
Chhattisgarh.
2. Agriculture Insurance Co. Of India Ltd. Raipur, Through Its Manager, Address- Jivan
Prakash, Jivan Bima, Marg, Pandary , Raipur, Tahsil And District- Raipur,
Chhattisgarh.
3. Aadim Jati Sewa Sahkari Samiti Maryadit Through Its Manager, Tahsil- Marwahi,
District- Gaurela- Pendra- Marwahi, Chhattisgarh.
---- Respondents
For Petitioner
:
Mr. Badruddin Khan, Advocate
For Respondent/ State
:
Mr. Anmol Sharma, PL.
Hon'ble Shri Justice
Goutam Bhaduri
Order On Board
04/10/2021
Heard.
1. The claim of the petitioner in the present petition is that the petitioner is covered as
beneficiary under the Pradhan Mantri Fasal Beema Yojna. Learned counsel for the
petitioner submits that in the year 2019, due to shortfall in the rain, the father of the
petitioner could not get the adequate crop which was insured and since the crop was
insured, therefore he would be entitled to get the benefit of Pradhan Mantri Fasal
Beema Yojna to be compensated. It is stated that this is the second round of
litigation. On the earlier round of litigation, this Court, in WPC No. 2311/2020 in the
case of Birbal Singh Banafar (who is father of the petitioner) on 08.10.2020, had
directed to file a representation before the concerned Collector which was further
directed to be decided. Subsequently, on the representation having been filed, the
same was dismissed on the ground that father of the petitioner has procured more
than the threshold limit of the crop meaning thereby the crop procured was more
than the minimum limit of capacity earmarked to get the benefit of insurance.
Thereby would be disentitled to get the benefit under the Pradhan Mantri Fasal
Beema Yojna. He further submits that the said order is bad in law, inasmuch as the
petitioner along with other is entitled to get the benefit for the reason that they have
only procured the minimum threshold limit of 1664 kg. of crop per hectare at village
Jhirnapondi.
2. The perusal of order dated 09.12.2020 would show that there is a factual dispute
which has come up. Prima facie in the case of Birbal Singh Banafar (who is father of
the petitioner), the procurement was 2223 kg. crop per hectare at village
Jhirnapondi. Therefore, since the yield was said to be more than the minimum
threshold crop limit, the claim of father of the petitioner was dismissed. In any case,
the disputed question of facts are required to be decided. At one hand, according to
the petitioner, father of the petitioner procured only the minimum threshold limit
whereas the Government has come up by dismissing father of petitioner's
application claiming that the crop procurement at village were more than the
threshold crop limit. These factual aspects are required to be substantiated by the
ancillary evidence. As per the State Government, like nature of grievances can be
redressed by the District Level Grievance Redressal Committee as per the
notification dated 16.06.2020. Therefore, since the disputed question are required to
be settled and already the forum has been created by the State, the petitioner can
approach the District Level Grievance Redressal Committee along with all the
relevant documents within a period of 45 days. In such case, if such application is
filed, it would be decided in accordance with the facts which are available on record.
3. With the aforesaid observation/ direction, the writ petition stands disposed off.
Sd/-
(Goutam Bhaduri)