BOMBAY HIGH COURT - APPELLATE SIDE,BOMBAY
UNION OF INDAI – Appellant
Versus
M/S. K.R. TRADERS AND ANR – Respondent
ARA 8/2009
1/48 ARBITARTION APPEAL NO. 8 OF 2009.sxw
hvn
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION APPEAL NO. 8 OF 2009
IN
APPEAL NO. 798 OF 2005
IN
AWARD DATED 19TH JUNE, 2005
Union of India,
Through the Chief Engineer (AF),
Camp Hanuman, Ahmedabad through
Shri. R.N. Singh, (CWE (AF) Lohogaon,
Pune) authorized signatory on behalf of
Chief Engineer (AF), Ahmedabad
… Appellants
Versus
1. M/s. KR. Traders,
G-3/4, Camellias Green Acres,
Salunke Vihar Road, Kondhwa,
Pune.
2. Shri. S.G. Mahajan,
Sole Arbitrator,
15, Swastishree Society,
Ganesh Nagar, Pune
… Respondents
Mr. S.R. Rajguru with Mr. A.R. Varma for the appellant.
Mr. A.A. Kumbhakoni, Mr. Ashutosh Gawnekar and Mr. Abhay Anturkar i/by
Mr. L.M. Acharya for respondents.
CORAM : R.D. DHANUKA, J.
RESERVED ON : NOVEMBER 23, 2012.
PRONOUNED ON : JANUARY 22, 2013.
ORAL JUDGMENT :
1.
By this appeal filed under section 37 of the Arbitration &
Conciliation Act, 1996 (for short hereinafter referred to as Act), the appellant
2/48 ARBITARTION APPEAL NO. 8 OF 2009.sxw
seeks to challenge the order and judgment dated 23rd October, 2008 passed
by the District court, Pune rejecting the Arbitration Application filed by the
appellant under section 34 of the Act. The appellants are hereinafter referred
to as UOI and respondents are hereinafter referred to as Contractors for the
sake of convenience. The UOI had impugned the award dated 19th June,
2005 made by the learned arbitrator allowing some of the claims with interest
of the contractor and rejected the counter claims made by the UOI. The
contractor was claimant in the arbitral proceedings and the UOI was
respondent. Some of the relevant facts which are necessary for the purpose
of deciding this appeal are as under :
(a)
Some time in the year 1992, the UOI invited tenders for
providing specialized technology accommodation at Air Force Station,
Pune. The contractor submitted its tender for the said work. The bid of
the contractor was accepted by UOI for the contract amount of
Rs.4,75,27,093.05. Both the parties accordingly entered into formal
contact on 28th September, 1992. The UOI issued work order in
furtherance of the said contract on 10th October, 1992. The stipulated
date for commencement of the work was 13th October, 1992 and the
stipulated date for completion was 12th October, 1994. Time to
complete the work was extended from time to time by UOI on the
request made by the contractor. The last extension was granted till
20th April, 1997. The contractor completed the said work on 20th April,
1997. The work was certified by the UOI by its letter dated 27th April,
3/48 ARBITARTION APPEAL NO. 8 OF 2009.sxw
1997.
(b)
The contractor used to submit running account bills from
time to time. The contractor by its letter dated 23rd March, 2001 called
upon the UOI to pay various outstanding dues payable to the
respondent. The contractor by its letter dated 25th July, 2001 invoked
arbitration clause and requested for appointment of the arbitrator to
adjudicate the disputes which had arisen between the parties. The UOI
however, did not appoint the arbitrator. The contractor thereafter filed
an application being Arbitration Application (4 of 2002) under section 11
of the Act in this court for appointment of the arbitrator. It is the case of
the contractor that inspite of the assurances given by the UOI before
this court to appoint sole arbitrator, the UOI did not appoint any
arbitrator. The contractor filed another arbitration application before
this court for appointment of the arbitrator. By consent of both the
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.