M.S.E.B – Appellant
Versus
M/S GURUKRUPA BUILDERS – Respondent
FA 1145/1992
1 fa1145-46-92j
rpa
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURSIDICTION
FIRST APPEAL NO. 1145 OF 1992
ALONGWITH
FIRST APPEAL NO. 1146 OF 1992
Maharashtra State Electricity
.. Appellant in
Board, Kalwa
both Appeals
V/s.
M/s. Gurukrupa Builders,
.. Respondent
Ulhasangar – 2, Dist.- Thane
both Appeals
.....
Ms. A.R. S. Baxi for the Appellant in both Appellant.
None for the Respondent.
.....
CORAM : A.S.OKA, J.
DATE : SEPTEMBER 12, 2011.
ORAL JUDGMENT :
Heard the learned Counsel appearing for the
Appellant in support of the Appeal. There were two suits
filed by the Respondent being Special Civil Suit No.46 of
1985 and Special Civil Suit No.226 of 1986. The Appellant
MSEB had invited tenders for work of construction of
permanent rail track in 400/200 KV-Sub-Station at Kalwa,
District Thane. The tender was filled in by the
Respondent-plaintiff. The tender of the Respondent was
accepted. Work order was issued to the Respondent on
14th May, 1979. The cost of work was Rs.7,25,257.65 and
2 fa1145-46-92j
the work was to be completed within a period of two
months from the date of handing over the site. Further
work of pile foundation was given to another contractor.
In Special Civil Suit No. 46 of 1985, it was contended that
there was delay on the part of the Appellant in handing
over the site and, therefore, the Respondent could not
commence the work. It was alleged that day to day work
drawings were not provided to the Respondent. It was
alleged that the Appellant did not hand over the mild steel,
cement, and other material to the Respondent in time.
Reliance is placed on the correspondence made by the
parties. It is alleged that by the letters dated 8th April,
1990 and 22nd April, 1990, the contract was terminated by
the Appellant. It is alleged that without offering a
reasonable opportunity to explain, the contract was
terminated. Under the terms of the contract, the
Respondent has furnished a bank guarantee in the sum of
Rs.52,266/-. It is alleged that the Appellant tried to invoke
the Bank guarantee of Rs.52,266/-. A reference is made to
the letter dated 11th February, 1985 issued by the Appellant
for invoking the Bank Guarantee. The prayer in the first
suit i.e. Special Civil Suit No.46 of 1985 is that the letter
dated 11th February, 1985 issued by the Executive Engineer
3 fa1145-46-92j
of the Appellant be declared as ineffective, illegal and
contrary to the terms of contract. The second prayer is of
perpetual injunction restraining the Appellant from
recovering the amount covered by the Bank Guarantee of
Rs.56,266/-. The suit was contested by filing written
statement. It was contended that there was no default on
the part of the Appellant. It was contended that by letter
dated 4th August, 1980, the Appellant called upon the
Respondent to remit a sum of Rs.74,500/- towards risk
and costs. It was contended that as the Respondent has
committed breach of contract, the Appellant was entitled to
invoke the Bank Guarantee.
2.
During the pendency of the said earlier suit, the
Respondent filed a suit for recovery of a sum of
Rs.2,55,783.30 against the Appellant. The said claim was
made on account of balance amount of third running bill,
the work done after the third running bill, extra work
done, increase in costs of materials, costs of overheads and
establishment expenses. Interest was prayed for at the rate
of 18% per annum from the date of the notice till the filing
of the suit. The said amounts were claimed on the ground
of alleged illegal termination of the contract by the
Appellant. The prayer in the second suit is for declaration
4 fa1145-46-92j
that letter dated 22nd April, 1980 issued by the Appellant of
termination of the co
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.