HIGH COURT OF BOMBAY
SAYYAD MOHAMAD JAVED – Appellant
Versus
THE STATE OF MAHARASHTRA AND ORS – Respondent
WP 4960/2021
32. WP 4960 of 2021.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 4960 OF 2021
(Sr. No. 32)
Sayyad Mohammad Javed
...Petitioner
vs.
The State of Maharashtra and Ors.
...Respondents
WITH
WRIT PETITION NO. 4961 OF 2021
(Sr. No. 33)
Parag Shripatrao Mate and Anr.
...Petitioners
vs.
The State of Maharashtra and Ors.
...Respondents
WITH
WRIT PETITION (ST.) NO. 14125 OF 2021
Tanaji Baban Parkhi
…Petitioner
Vs.
The State of Maharashtra and Ors.
...Respondents
Mr. Sandeep D. Shinde i/by Ergo Juris, for the Petitioner
Mr. R. S. Pawar – AGP for the Respondent-State in WP 4960 of 2021
Ms. M. S. Bane – AGP for the Respondent-State in WP 4961 of 2021
R. M. Shinde – AGP for the Respondent-State in WP(ST) 14125 of 2021
CORAM :
PRASANNA B. VARALE &
S. M. MODAK, JJ.
DATE :
18th NOVEMBER, 2021
PER COURT:-
.
Writ Petition (ST) No 14125 of 2021 not on board. Taken on
Seema
1/5
SEEMA
KSHITIJ
YELKAR
Digitally signed
by SEEMA
KSHITIJ
YELKAR
Date:
2021.12.04
11:01:27 +0530
32. WP 4960 of 2021.doc
board.
2.
At the outset learned counsel for the Petitioner submits that the
petition bearing Writ Petition (ST) No. 14125 of 2021 also involves
identical issue and as such Writ Petition (ST) No. 14125 of 2021 be
tagged alongwith present Writ Petitions.
3.
Considering the limited issue involved in this Writ Petitions, by
consent of both the sides we have taken up these Writ petitions for final
hearing at the admission stage itself. Admit.
4.
Respondent Nos. 2 to 6 are the executives of Respondent No. 1-
State. There is no private Respondent. Accordingly, we have heard the
learned counsel for the Petitioners and learned AGP for all the
Respondents.
5.
The short issue involved in these petitions and it is for how much
duration the agricultural land belonging to the Petitioners can be
subject to restrictions? The agricultural land is situated at Mauje Maan,
Taluka Mulshi, District Pune and its revenue Gat No. 70/1,
admeasuring 01 Hectares 81 Ares land situated ad Mauje Man, Taluka
Mulshi, District Pune, in Writ Petition No. 4960 of 2021 and and its
revenue Gat No. 165/1, admeasuring 2 H 15 Ares land situated ad
Mauje Maan, Taluka Mulshi, District Pune in Writ Petition No. 4961 of
2021. There are names of other persons mentioned on 7/12 extract.
But they are not the Petitioners.
Seema
2/5
32. WP 4960 of 2021.doc
6.
The Respondent No. 1-State has issued notification thereby
reserving certain lands at village Mauje Maan, Taluka Mulshi, District
Pune being the lands reserved for the purpose of acquiring the land for
rehabilitating the project affected persons of Kasarsai Project. Amongst
several lands, the land described above is one of the lands. Thus,
notification was issued in the year 1992 and 1999. The revenue officers
have given effect to the said notification by making an entry in other
right column of 7/12 extract as land reserved for the rehabilitating
project affected persons of Kasarsai Project. Necessary mutation entries
were done in the year 1992 and 1999 respectively.
7.
The Petitioners come with grievance that in spite of such entries,
the Respondents have not taken further steps in acquiring the land for
the purpose for which it was reserved. It continues till 2021. That is
why these Writ petitions for issuing necessary directions to the
Respondents to remove that remark from other right column of 7/12
extract. There is a Government Resolution dated 5th August 2019
governing the field. It lays down the procedure for withdrawing the
restrictions imposed in respect of dealing with the land reserved for the
project affected person. According to the Petitioners in respect of this
Government Resolution for the last two years, no steps have been
taken.
8.
When we are heard learned AGP, with limited instructions
available at his disposal, he has not come with a submission that all
these years any steps are taken for acquiring lands in question.
Seema
3/5
32. WP 4960 of 2021.doc
9.
As per the said