HIGH COURT OF BOMBAY
SACHIN OMPRAKASH BAJAJ – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
WP 6889/2015
['BHANDARI ANAND P', 'DEVE S S', '', 'COPY SERVED ON GP', 'GP']
wp6889.15
(1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.6889 OF 2015
Sachin Omprakash Bajaj,
Age : 36 YEARS, Occu. Agriculturist,
R/o Zenda Chowk,
Majalgaon, Tq. Majalgaon, Dist. Beed
..PETITIONER
VERSUS
1.
The State of Maharashtra,
Through its Secretary,
Industries and Labour Department,
Mantralaya, Mumbai-32
2.
Sub-Divisional Officer and
Land Acquisition Officer,
Ambajogai, Dist. Beed
3.
Maharashtra Industrial Development
Corporation, Aurangabad
Through its Divisional Officer
4.
Sub-Divisional Officer,
Majalgaon
..RESPONDENTS
Mr A.P. Bhandari, Advocate for petitioner;
Mr S.R. Yawalkar, A.G.P. for respondent nos.1, 2 & 4;
Mr S.S. Deve, Advocate for respondent no.3
CORAM : RAVINDRA V. GHUGE
AND
S. G. MEHARE, JJ.
DATE : 24th August, 2021
ORAL JUDGMENT (Per Ravindra V. Ghuge, J.)
1.
Leave to add Sub-Divisional Officer, Majalgaon as respondent no.4.
Addition be carried out forthwith. Issue notice to respondent no.4. The
learned A.G.P. waives service and causes an appearance on behalf of
said respondent.
wp6889.15
(2)
2.
Rule. Rule made returnable forthwith and heard finally by the
consent of the parties.
3.
By this petition, the petitioner has putforth prayer clauses (B), (D)
and (E) as under:-
“(B)
By appropriate writ, order or direction, order dated
29.12.2012 passed by respondent no.2 in File
no.2010/LNQ/MIDC/CR/WS7540 under section 33 (2) and 36
(1) (Exhibit E) be quashed and set aside to the extent of land
bearing Survey no.53, to the extent of 53 R situated at village
Dhangarwadi, Tq. Majalgaon, Dist. Beed
(D)
By appropriate writ, order or direction, the respondent
authorities be directed to initiate the proceedings for
acquisition of land, in accordance with provisions of section 33
(3) and 33 (4) of the MID Act, 1961 and pass appropriate
award by following due process of law.
OR IN THE ALTERNATIVE
(E)
By appropriate writ, order or direction, the respondents
be directed to delete the land of the petitioner from notified
MIDC area, Dhangarwadi, Tal. Majalgaon, Dist. Beed.”
(There is no prayer clause (C)
4.
We have considered the extensive submissions of the learned
Advocate for the petitioner, the learned A.G.P. on behalf of respondent
nos.1, 2 and 4 and the learned Advocate on behalf of respondent no.3. It
wp6889.15
(3)
has been brought to our notice that in practically identical set of facts, this
Court has delivered a judgment on 24th December, 2017 in Writ Petition
No.285 of 2012 filed by Shri Vitthaldas Tribhuvandas Bagadia and anr.
vs. State of Maharashtra & ors.
5.
The sequence of events in relation to the land at issue are as
under:-
a)
In July, 2010, the petitioner purchased the said land from the
original owner.
b)
On 4th November, 2010, the notification under Section 32 (1) of the
Maharashtra Industrial Development Act, 1961 (for short “MID
Act”) was published.
c)
By virtue of Section 32 (4), the land is deemed to be vested in the
Government free from all encumbrances from the date of the
publication of the notice under Section 32 (1)
d)
In December, 2010, the petitioner moved an application for seeking
the NA 44 order which was granted.
e)
On 29th December, 2012, the award was delivered by respondent
no.2 and compensation amount was deposited in the Treasury.
wp6889.15
(4)
f)
The respondent authorities are unable to locate any agreement
signed with the petitioner with regard to quantification of the
compensation amount.
g)
The contention of the petitioner is that the land could not have been
taken over by the authorities in the absence of an agreement.
h)
A notice under Section 32 (5) of the MID Act, dated 29th December,
2012 was served upon the petitioner