HIGH COURT OF BOMBAY
JIJAMATA PUBLIC SCHOOL THROUGH AUTHORIZED SIGNATORY – Appellant
Versus
EMPLOYEES PROVIDENT FUNDS ORGANIZATION THR THE REGIONAL PROVIDENT FUNDS COMMISSIONER – Respondent
WP 9975/2021
1 WP9975.2021
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD.
WRIT PETITION NO. 9975 OF 2021
Jijamata Public School
Dnyaneshwarnagar, Bhenda (Bk),
Tq. Newasa, Dist. Ahmednagar,
Through Authorized Signatory
...Petitioner
Versus
Employees Provident Funds Organization,
through the Regional Provident Funds
Commissioner, SRO Plot No. 11,
Bhavishya Nidhi Bhavan,
MIDC Satpur, Nashik.
...Respondent
.....
Mr. V. N. Upadhye, Advocate for the petitioner
Mr. N. K. Chaudhari, Advocate for respondent-sole
..…
AND
WRIT PETITION NO.9988 OF 2021
Jijamata Krushi Tantra Vidyalaya,
Dnyaneshwarnagar, Bhenda (Bk),
Tq. Newasa, Dist. Ahmednagar,
Through Authorized Signatory
...Petitioner
Versus
Employees Provident Funds Organization,
through the Regional Provident Funds
Commissioner, SRO Plot No. 11,
Bhavishya Nidhi Bhavan, MIDC Satpur, Nashik. ...Respondent
.....
Mr. V. N. Upadhye, Advocate for the petitioner
Mr. N. K. Chaudhari, Advocate for respondent-sole
SG Punde, PA
2 WP9975.2021
..…
CORAM : BHARATI H. DANGRE, J.
DATE : JANUARY 20TH, 2022
ORAL JUDGMENT : -
1.
Rule. Rule made returnable forthwith. Heard finally with
the consent of the parties.
2.
The two petitioners are the public schools run by a public
trust established in the year 2003 and has engaged itself into the
activity of imparting education. The petitioners initially did not
succumb themselves to the provisions of the Employees Provident
Funds and Miscellaneous Provisions Act, 1952 (hereinafter referred
to as “the Act, 1952”), however, pursuant to the Ministry of Labour
and Employment issuing a scheme in the form of a special provision
in respect of employees’ Enrollment Campaign, 2017 in exercise of
the powers conferred by Section 5 read with sub-section 1 of Section
7 of the Act, 1952 by which the existing Employees’ Provident Funds
Scheme, 1952 came to be amended, the petitioners offered
voluntarily to cover it’s employees under the provisions of the Act
through ORLE portal of the Department under Section 2-A of the Act,
1952. The petitioners on their own submitted their willingness to
SG Punde, PA
3 WP9975.2021
fulfill the requirements of the scheme and accordingly remitted the
contributions in terms of the scheme, somewhere in July-2018 and
they were allotted separate code for remittances and other purposes.
The date of coverage was declared as 16.06.2003 and the petitioners
remitted the contribution/EPF dues including employees and
employer’s share for the period from June-2003 to August-2018 in
the month of July-2018.
3.
The case of the petitioners is, while they subjected
themselves to the provisions of the Act, 1952 in the wake of the
special scheme, the assurance was given that there would be no levy
of any penalty, interest and/or damages etc., against them but
surprisingly, according to the petitioners, on 26.11.2019, the
respondent initiated inquiry under Section 14-B read with Section 7Q
of the Act, 1952 and the notice asked them to show cause as to why
damages and interest for the late remittance should not be fastened
upon them.
4.
The notice issued by the Provident Fund Commissioner,
Ahmednagar addressed to the petitioners state that the petitioners -
establishment is covered under the Act, 1952 and in terms of the
SG Punde, PA
4 WP9975.2021
provisions of the Act, 1952 r/w the Employees Provident Funds
Scheme, 1952 [for the sake of brevity “Scheme of 1952”], the
employer-establishment is required to remit the contributions along
with the administrative charges withi