HIGH COURT OF BOMBAY
MAHARASHTRA ENGINEERS ASSOCIATION REGISTRATION NO NSK 781 THRO ITS GENERAL SECRETARY – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
PIL 110/2016
['PALODKAR DEVDATT P', 'COPY SERVED ON GP', '', 'GP']
*1*
16.pil.110.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
PUBLIC INTEREST LITIGATION NO. 110 OF 2016
MAHARASHTRA ENGINEERS ASSOCIATION REGISTRATION NO NSK781
THRO ITS GENERAL SECRET
VERSUS
THE STATE OF MAHARASHTRA AND OTHERS
...
Advocate for Petitioner : Shri Palodkar Devdatt P.
AGP for Respondents / State : Shri A.R.Kale.
...
CORAM: S.C. DHARMADHIKARI
AND
MANGESH S. PATIL, JJ.
DATE :- 12th June, 2017
P.C.:
1
The Maharashtra Engineers Association which represents,
according to the cause title, the registered members/ contractors, has filed
this petition alleging that on account of the Government Resolution dated
12.07.2016, an exemption was granted from e-tendering process for the
works to be carried out from the funds of the Members of Parliament (MP)
or Members of State Legislature (MLA) in the garb that the works from
their funds and upto to the ceiling limit of Rs.10 lac have to be completed
expeditiously.
2
This has been construed by the Petitioner Association as an
*2*
16.pil.110.16
exemption from normal and general rule of e-tendering, which e-
tendering process according to the Petitioner brings about complete
transparency and leaves no scope for any unfairness, unreasonableness,
discrimination and malafides.
3
Another petition being Writ Petition No.7954/2016 pending
in this Court and the order made therein on 16.03.2017 is relied upon to
urge that this Court should proceed to quash and set aside this
Government Resolution though it is a policy decision.
4
Possibility of abuse of power, by no means, gives rise to the
cause of action and enabling the High Court to interfere with the policy
decision. Possible misuse and abuse of power is thus, no ground to
interfere in writ jurisdiction when right from the judgment in the case of
Matajog Dobey vs. H.C.Bhari (AIR 1956 SC 44) there is a presumption that
every Government action and decision is fair, reasonable and just. There
has to be material on record so as to interfere with the policy decision and
which would demonstrate blatant acts of favouritism, nepotism and
malafides and where it is generally alleged that MPs/ MLAs are securing
contracts for their own people and therefore, on their requests/ letters or
recommendations the contracts are awarded.
5
In the present petition, there is no pleading much less any
concrete example or illustration from any part of the Marathwada region
that there are such recommendations/ requests from the MPs/ MLAs. We,
*3*
16.pil.110.16
therefore, grant leave to the Petitioner's advocate to bring on record such
material and only then we will scrutinize any action of the State.
6
Place this matter along with Writ Petition No.7954/2016 on
10.07.2017.
(MANGESH S. PATIL, J.)
(S.C. DHARMADHIKARI, J.)
kps