BOMBAY HIGH COURT - BENCH AT GOA
THE VILLAGE PANCHAYAT OF BETQUI-CANDOLA, THROUGH ITS SARPANCH, CANDOLA – Appellant
Versus
M/S GOAN PARADISE, THROUGH ITS POA MR. MAHESH ADWALPALKAR AND 3 ORS – Respondent
WP 662/2015
['ADV NIGEL DA COSTA FRIAS', '', 'ADV PRATIKSHA NAGVEKAR', 'ADV IVINA MIRANDA']
WP No. 662/2015
1
IN THE HIGH COURT OF BOMBAY AT GOA
WRIT PETITION NO. 662 OF 2015
The Village Panchayat of Betqui-Candola,
Through its Sarpanch,
Candola, Ponda, Goa.
… Petitioner
Versus
1.
M/s Goan Paradise,
Through its POA
Mr. Mahesh Adwalpalkar,
Major, with office at
3rd Floor, Patto Center,
EDC Complex, Panaji, Goa.
2.
The Deputy Director of Panchayats,
North Goa, Junta House,
Panaji, Goa.
3.
The Additional Director of Panchayats-II,
North Goa, Junta House,
Panaji, Goa.
4.
The State of Goa,
Through its Chief Secretary,
Secretariat, Porvorim, Goa.
… Respondents
***
Shri Nigel Da Costa Frias, Advocate for the Petitioner.
Shri S.D. Lotlikar, Senior Advocate with Shri J. Simoes Advocate for
the Respondent No. 1.
None for Respondent Nos. 2, 3 and 4.
WP No. 662/2015
2
CORAM:- C. V. BHADANG, J.
RESERVED ON:- 1
st SEPTEMBER, 2015.
PRONOUNCED ON:- 2
nd
/4
th SEPTEMBER, 2015.
JUDGMENT:
Rule. Rule made returnable forthwith. Shri Simoes,
learned Counsel waives service on behalf of respondent no. 1.
None for respondent nos. 2, 3 and 4. Heard finally by consent.
2.
By this petition, the Village Panchayat of Betqui-Candola
is challenging the judgment and order dated 07.08.2015 passed by
the respondent no. 3, thereby confirming the order dated
08.07.2015 passed by the respondent no. 2, directing the
petitioner to grant permission/renewal of the construction license
to the respondent no. 1.
3.
The brief facts necessary for the disposal of the petition
may be stated thus:
That, respondent no. 1 had applied for a license for
construction of residential cum commercial complex and compound
wall in Survey No. 112 (part) of village Candola, Ponda, Goa. That
license, was issued by the petitioner on 10.02.2012. That license,
WP No. 662/2015
3
was signed by the Sarpanch of the petitioner-Village Panchayat.
The said license was valid for a period of three years.
On 07.02.2015, the respondent no. 1 applied for
renewal of the license and submitted a revised plan. According to
the petitioner, the revised plan showed the Sewage Treatment
Plant (STP) in the proposed complex. However, the respondent no.
1 had not produced the consent from the Goa State Pollution
Control Board.
On 26.05.2015, the respondent no. 1 sought return of
the proposal/file stating that, it would be re-submitted after
obtaining the approval of Primary Health Centre. It appears that
on 28.05.2015 the application/proposal for renewal/approval of the
revised plan was re-submitted alongwith No Objection Certificate
(NOC) from the Health Officer. On 15.06.2015, the petitioner
passed a resolution seeking clarification from respondent no. 1 on
certain aspects. The respondent no. 1 instead of replying the
same, filed an appeal under Section 66(2) of the Goa Panchayat
Raj Act, 1994 (the Act of 1994, for short) before the Deputy
Director on 15.06.2015. On 07.07.2015, a joint site inspection
was proposed. Ultimately, the Appellate Authority by order dated
WP No. 662/2015
4
08.07.2015 directed the petitioner to grant renewal of the
construction license dated 10.02.2012 for residential cum
commercial complex (revised plan) as per technical clearance
dated 06.02.2015 issued by the Town and Country Planning
Department, Ponda, Goa. The petitioner was directed to grant the
renewal within six days from the date of the order. Incidentally,
the order stipulates that the Secretary of the Village Panchayat
shall execute the order in terms of Section 47-B of the Act of 1994.
It is undisputed that in pursuance to the said order dated
08.07.2015, the petitioner had granted permission on 11.08.2015,
which is signed by the Secretary of the Panchayat. Feeling
aggrieved, by the order of the Deputy Director, the petitioner
challenged the same before the Additional Director of Panchayat in
an appeal under Sectio