MADRAS HIGH COURT
SATHISH @ OTTA SATHISH – Appellant
Versus
THE SUB DIVISIONAL MAGISTRATE CUM REVENUE DIVISIONAL OFFICER – Respondent
CRL MP 200/2022
/ 1 /
IN THE HIGH COURT OF JUDICATURE AT MADRAS
(ORDINARY ORIGINAL CIVIL JURISDICTION)
TUESDAY, THE 21ST DAY OF JUNE 2022
THE HON'BLE MR. JUSTICE M.SUNDAR
ARB .O.P(COM.DIV.) No.200 of 2022
In the matter of Arbitrtion and
Conciliation Act, 1996
and
In the matter of Arbitration
agreement dated 12.04.2012
Between M/s.DEE-TECH
PROJECTS PVT.LTD. And
M/S.BATLIBOI
ENVIRONMENTAL
ENGINEERING LTD.,
* M/S. DEETECH PROJECTS PVT.LTD.
Rep.by its Managing Director, Mr. S.Sivaraman,
No.129, 2nd Floor, Aani Street,
Chinmaya Nagar,
Chennai -600 092
* (Amended as per order dated-28.4.2022
in A.No.1912/2022).
..Petitioner
-Vs-
M/S.BATLIBOI ENVIRONMENTAL ENGINEERING LTD.,
Represented by its Divisional Manager
Mr. Vilas M. Gharat
SPARTAN HOUSE,
1st Floor, Plot No. B/29,
Road No.18/S,
/ 2 /
Wagle Estate,
Thane (W) – 400604
..Respondent
Arbitration Original Petition (Commercial Division) praying that
this Hon'ble court be pleased to appoint an arbitrator for adjudicating the
dispute arising between the applicant and respondent in respect to the work
order that was awarded to the consortium vide LOA No.
CMWSSB/CNT/C2/W/CNT/SEW/NCB/JNNURM/122/2010-2011, dated
21.11.2011.
This Arbitration Original Petition (Commercial Division)
coming on this day before this court for hearing the court made the
following order:
Captioned 'Arbitration Original Petition' [hereinafter 'Arb. OP' for
the sake of convenience and clarity] has been presented in this Court on
04.04.2022 with a prayer for appointment of an Arbitrator.
2. Mr.A.Praveen Alexander, learned counsel for petitioner who is
before this Court submits that captioned Arb.OP is predicated on Clause 11
captioned 'DISPUTE' in an agreement captioned 'CONSORTIUM
AGREEMENT dated 12.04.2012' (hereinafter 'primary contract' for the sake
/ 3 /
of convenience and clarity).
3. Clause 11 of primary contract serves as arbitration agreement
between the petitioner and respondent i.e., arbitration agreement within the
meaning of Section 2(1)(b) read with Section 7 of 'The Arbitration and
Conciliation Act, 1996 (Act 26 of 1996)' [hereinafter 'A and C Act' for the
sake of brevity, convenience and clarity] is learned counsel's say.
4. Learned counsel submits that primary contract was with regard
to a tender floated by 'Chennai Metropolitan Water Supply and Sewerage Board'
['CMWSSB' for the sake of convenience and clarity] and work that has to be
done thereunder. Learned counsel submits that primary contract ran into
rough weather and arbitrable dispute erupted owing to alleged lack of
interest on the part of the respondent leaving it to the petitioner to complete
the project in full. It is not necessary to dilate further on arbitrable disputes
as this is a Section 11 legal drill which has to perambulate within the
statutory perimeter sketched by sub-section (6A) thereat. Suffice to say that
a notice invoking arbitration being 'notice dated 12.03.2022' ('trigger notice'
for the sake of convenience) was issued by the petitioner and this was duly
served on the respondent on 17.03.2022. There has been no response from
the respondent necessitating the presentation of captioned Arb.OP in this
Court on 04.04.2022 is learned counsel's further say.
/ 4 /
5. Prima facie case for issue of notice made out.
6. Issue notice to respondent returnable by a fortnight i.e.,
returnable by 05.07.2022. Private notice permitted.
List on 05.07.2022.
Sd/.M.S.J.
21.06.2022
//Certified to be a true copy//
Dated at Madras this the day of 2022.
SU./28.06.2022 COURT OFFICER(O.S.)
From 25.09.2008 the Registry is issuing certified copies of the
Orders/Judgments/Decrees in this format.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.