HIGH COURT OF JUDICATURE AT MADRAS
THE PUBLIC INFORMATION OFFICER – Appellant
Versus
SUBRAMANI – Respondent
CRP 1548/2020



Advocates:
['M/S AIYAR AND DOLIA', 'THRO LCC M/S V C JAYASANKAR', 'ADVOCATE', '', 'AOS NOT FILED', '', 'PVT NOTICE', 'R- THE DISTRICT COLLECTOR DISTRICT COLLECTOR OFFICE', 'TIRUPPUR']

C.R.P. No.1548 of 2020 & CMP No.9286 of 2020

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 11.10.2022

CORAM:

THE HONOURABLE MRS.JUSTICE R. HEMALATHA

C.R.P. No.1548 of 2020

& CMP No.9286 of 2020

The Public Information Officer/

The Assistant General Manager,

Power Grid Corporation of India Ltd.,

400/230 KV Sub Station

Coimbatore Main Road

K. Paramathi Post

Karur District

... Petitioner

Vs.

1. Subramani

2. The District Collector

District Collector Office

Tiruppur

... Respondents

Prayer: Civil Revision Petition filed under Article 227 of Constitution of

India praying to strike off the plaint in O.S. No.30 of 2020 on the file of

District Munsif Court, Dharapuram.

For Petitioner

: Mr. V. Kalyanaraman

for M/s. Aiyar and Dolia

For R2

: Mr. P. Harish, Government Advocate

1/4

https://www.mhc.tn.gov.in/judis

C.R.P. No.1548 of 2020 & CMP No.9286 of 2020

ORDER

This revision petitions is filed praying to strike off the plaint in

O.S. No.30 of 2020 on the file of District Munsif Court, Dharapuram.

2. The revision petitioner is the 1st defendant in O.S. No.

30/2020 on the file of the District Munsif, Dharapuram. The 1st

respondent/plaintiff filed a suit for a permanent injunction restraining the

revision petitioner/1st defendant and the District Collector, Tiruppur, from

trespassing into his property and putting up High Tension wires over his

property and for costs.

3. When the matter was taken up today for hearing, the learned

counsel appearing for the revision petitioner submitted that during the

pendency of the suit, High Tension Wires have been erected and the land

owners have been compensated adequately. He would further contend

that as per Section 145 of the Electricity Act, no Civil Court shall have the

jurisdiction to entertain any suit or grant any injunction in respect of any

work being carried out by the petitioner.

2/4

https://www.mhc.tn.gov.in/judis

C.R.P. No.1548 of 2020 & CMP No.9286 of 2020

4. It is further submitted by the learned counsel for the revision

petitioner that the 1st respondent/plaintiff received land compensation of

Rs.1,40,653/- and crop compensation of Rs.1,21,983/- and high tension

transmission lines have been commissioned on 14.05.2020. Therefore,

according to him, nothing survives for further adjudication in the suit in

O.S. No.30/2020 and consequently the present Civil Revision Petition has

become infructuous and hence the same may be closed.

5. In view of the submissions made by the learned counsel for

the revision petitioner/1st defendant, this Civil Revision Petition is disposed

of as having become infructuous. No costs. Consequently connected

miscellaneous petition is closed.

11.10.2022

Index

: Yes/No

Internet

: Yes/No

Speaking/non speaking

bga

3/4

https://www.mhc.tn.gov.in/judis

C.R.P. No.1548 of 2020 & CMP No.9286 of 2020

R.HEMALATHA, J.,

bga

To

1. District Munsif Court, Dharapuram.

2. The Section Officer, VR Section, High Court, Madras.

C.R.P. No.1548 of 2020

& CMP No.9286 of 2020

11.10.2022

4/4

https://www.mhc.tn.gov.in/judis

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top