HIGH COURT OF JUDICATURE AT MADRAS
Honourable Mr Justice R.VIJAYAKUMAR
2021 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT JUDGMENT RESERVED ON : 16.03.2022 JUDGMENT PRONOUNDED ON : 01.04.2022 CORAM: THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR S.A.(MD).No.479
D).No.479
S.A.(MD).No.479 of 2021
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
JUDGMENT RESERVED ON : 16.03.2022
JUDGMENT PRONOUNDED ON : 01.04.2022
CORAM:
THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR
S.A.(MD).No.479 of 2021
and CMP(MD).No.6418 of 2021
Muthulalitha
...Appellant/Appellant/
Plaintiff
Vs
Sundaravadivu
...Respondent/Respondent/
Defendant
PRAYER : Second Appeal is filed under Section 100 of C.P.C, to allow
the second appeal by setting aside the judgment and decree made in
A.S.No.29 of 2018 dated 08.02.2021 on the file of the Additional
District and Sessions Court, Srivilliputhur, confirming the judgment
and decree made in O.S.No.52 of 2010 dated 02.01.2018 on the file of
the Subordinate Court, Srivilliputhur.
For Appellant
: Mr.M.Thirunavukkarasu
For Respondent : Mr.S.Ramesh
For Mr.V.Raghavachari
JUDGMENT
The plaintiff is the appellant.
2.The plaintiff filed O.S.No.52 of 2010 before the
Subordinate Court, Srivilliputhur for declaration that she is the
absolute owner of the plaint second schedule property which is a
wall and sought for consequential permanent injunction from in any
way encroaching or doing any other construction in the plaint second
schedule property. The plaintiff further prayed for a mandatory
injunction to remove the encroachment over the second schedule wall
as shown in the plaint fourth schedule property.
3.The trial Court partly allowed the suit granting
declaration of title over the first and second schedule properties
and consequential injunction for the said properties. The trial
Court also granted permanent injunction in favour of the plaintiff
1/7
https://hcservices.ecourts.gov.in/hcservices/
S.A.(MD).No.479 of 2021
that the defendant should not put up any construction or encroach
over the second schedule property. However, the prayer with regard
to mandatory injunction was rejected. As against the same, the
plaintiff filed A.S.No.29 of 2018 before the Additional District and
Sessions Court, Srivilliputhur. The learned Appellate Judge
concurred with the findings of the trial Court and dismissed the
appeal filed by the plaintiff. As against the same, the present
second appeal has been filed by the plaintiff.
4.The plaintiff had contended that she is the owner of
plaint first and second schedule properties. The defendant who is
the adjacent owner had encroached upon the second schedule property
which is a wall belonging to the plaintiff and she has inserted ½
feet of her property at the height of 25 feet in the suit second
schedule wall and she has also put up 'RCC' tank in the said
encroachment. Hence, the plaintiff prayed for declaration and
permanent injunction for the second schedule property and for
mandatory injunction for removal of the encroachment ( mentioned in
the fourth schedule property) over the second schedule property.
5.The trial Court agreed with the contention of the
plaintiff that the suit second schedule property is the exclusive
wall belonging to the plaintiff and proceeded to grant a decree for
declaration of title and permanent injunction in favour of the
plaintiff over the second schedule property. The trial Court further
found that since the second schedule wall is the exclusive wall of
the plaintiff, the defendant is not entitled to put up any
construction over the second schedule wall. Hence, the trial Court
granted a decree for permanent injunction restraining the defendant
from in any manner put up any further construction or encroachment
over the second schedule wall. However, the prayer for mandatory
injunction for removal of construction that have already been was
rejected by the trial Court.
6.The trial Court relied upon the Advocate Commissioner's
report to arrive at a finding that the width of the second schedule
wall upto the first floor is 1 ½ feet and above the first floor, it
is o