HIGH COURT OF JAMMU & KASHMIR AND LADAKH
HON'BLE MR. JUSTICE ALI MOHAMMAD MAGREY
ABDUL SAMAD WANI AND ORS. – Appellant
Versus
UNION TERRITORY OF J AND K AND ORS. (JAL SHAKTI / PHE DEPARTMENT) – Respondent
WP(C)/1036/2021
Serial No. 114
Supplementary-1 List
HIGH COURT OF JAMMU AND KASHMIR
AT SRINAGAR
{Through Virtual Mode}
WP(C) No.1036 /2021
CM Nos.3415/2021 & 3416/2021
Abdul Samad Wani & Ors.
… Petitioner(s)
Through:
Mr Altaf Mehraj, Advocate.
Versus
Union Territory of Jammu and Kashmir & Ors.
… Respondent(s)
CORAM:
Hon’ble Mr Justice Ali Mohammad Magrey, Judge.
(ORDER)
31.05.2021
01.
The Petitioners claim to be registered Contractors with the
Respondent Department. In terms of e-NIT No. 35/PHEQ of 2020-21 dated
15th of February, 2021, the Respondent-Department invited e-enters for
execution of various works detailed out in the tender notice. The tender notice,
as stated, prescribed 2nd of March, 2021 as the last date for submission of bids
and 3rd of March, 2021 as the time of opening of technical bids. In response
to the aforesaid tender notice, the Petitioners, besides other eligible
Contractors, are stated to have submitted their tenders/ bids along with all
requisite documents before the Respondent-Department. It is pleaded that the
tender documents of the Petitioners were complete in all respects and that the
Page 2 of 10
WP(C) No.1036/2021;
CM Nos.3415/2021 & 3416/2021
Petitioners were, thus expecting positive results therefrom. Thereafter, the
technical bids were opened by the Respondent-Department, wherein, as
stated, the tender documents of the Petitioners were found responsive and the
process was initiated by the Respondent-Department for opening of financial
bids. However, the Petitioner No.2 is stated to have filed a complaint before
the Respondent No.4 with regard to the eligibility of the Respondent No.5, as
a consequence whereof, a Committee was constituted vide Order dated 12th of
April, 2021 and the process of allotment deferred. The Committee, on 26th of
April, 2021, submitted report whereby the Respondent No.5 was held eligible
to partake in the tendering process pursuant to the e-NIT in question.
Subsequently, on 27th of April, 2021, the Respondent No.5 was, upon opening
of financial bids, declared L1 and allotted the works put to tender in terms of
e-NIT dated 15th of February, 2021. Feeling aggrieved of the report of the
Committee constituted by the Respondent-Department qua eligibility of
Respondent No.5 as well as the subsequent decision of the Respondent-
Department to allot the works to Respondent No.5, the Petitioners have
challenged the vires of the same through the medium of the instant Writ
Petition before this Court under Article 226 of the Constitution of India.
02.
Mr Altaf Mehraj, the learned counsel for the Petitioners,
submitted that the report/ decision of the Committee constituted by the
Respondent-Department; whereby the Respondent No.4 has been found
eligible to participate in the tendering process and the subsequent allotment of
Page 3 of 10
WP(C) No.1036/2021;
CM Nos.3415/2021 & 3416/2021
works in favour of the Respondent No.5 pursuant to E-tender notice
No.35/PHEQ of 2020-21 is result of colorable exercise of power on part of
the Respondent-Department. It is submitted that the Petitioner No.2 had raised
an extremely important issue of ineligibility of Respondent No.5 qua non-
submission of requisite documents by the Respondent No.5 in tune with the
terms and conditions of the tender notice in question, however, the same was
not taken into consideration by the Committee constituted by the Respondent-
Department for the purpose. It is pleaded that the impugned action of the
Respondent-Department smacks of illegalities and malafides and, thus same
deserves to be set at naught.
03.
Heard the learned counsel for the Petitioners, perused the
pleadings on record and considered the matter.
04.
Admittedly, on the complaint of the Petitioner No.2 qua non-
submission of requisite documents by the Respondent No.5 along with his
tender document, the Respondent-Dep