HIGH COURT OF JAMMU & KASHMIR AND LADAKH
M/S KHANDAY INFRASTRUCTURE PRIVATE LIMITED – Appellant
Versus
UNION TERRITORY OF J AND K AND ORS. (PUBLIC WORKS DEPARTMENT) – Respondent
WP(C) 1529/2022
S. No. 108
Supplementary list 5
IN THE HIGH COURT 0F JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
WP(C) 1529/2022
M/S Khanday Infrastructure Private Limited
…Petitioner(s)
Through: Mr. S.A. Naik, Sr. Advocate
Vs.
U.T of J&K and Ors.
...Respondent(s)
Through: Ms. Insha Rashid, G.A.
CORAM:
HON’BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
ORDER
21.07.2022
1. The petitioner is a construction company and a registered
contractor. The petitioner is aggrieved of the communication of
Technical Officer to Executive Director JKPCC Limited, Srinagar,
bearing No. PS/ED/J/1581-86 dated 15th July 2022, addressed to
the
Deputy
General
Manager,
JKPCC
Limited,
Unit
Pulwama/Shopain, whereby a decision of the accepting authority
taken in terms of standard bidding document clause 53.2(c) and
53.4 of Section E of E-NIT dated 21st July 2020, and 19th April,
2021, with regard to the foreclosure of contracts at serial 1 and 2
and forfeiture of bank guarantee of the petitioner, has been
conveyed with a copy to the petitioner. The petitioner has also
been debarred from participation in future bidding in the JKPCC
Limited for one year. The impugned communication has been
challenged on several grounds.
2. The petitioner claims to have been allotted the construction work
of Trenz at Sheikhpora Bridge for Span 01 and 02, as also for Span
03, 04 and 05. The petitioner claims that despite various factors
causing disruption in the execution of the work, the petitioner
successfully completed the works in span 03 and 04, but due to
reasons beyond his control viz Covid-19 disturbances, observation
of the World Bank <ERA=, banning of oxygen cylinders, etc. the
execution of works of Span no. 01, 02 and 05 could not be
completed within the stipulated period.
3. The slow performance of the petitioner and its failure to complete
the works within time was placed before Contract Committee for
deliberations. The Accepting Authority took a decision to foreclose
the contracts for Span no. 1, 2 and Span no. 5, and forfeit the
Performance Security given in terms of bank guarantee dated 5th
October, 2020, drawn from Jammu and Kashmir Bank Unit
Qazigund, and Rupees 6,57,600/- deposited vide TDR No. 514482
dated 5th July, 2021, drawn from the same branch. The respondents
also debarred the petitioner from participating in bidding process
in JKPCC Limited for a period of one year.
4. It is this order which is called in question by the petitioner on the
ground that before foreclosing the contracts and acting under SBD
clause 53.2 (c) and 53.4 of Section E, no prior notice to show cause
and an opportunity of being heard was given to the petitioner. Mr.
S.A. Naik, learned counsel appearing for the petitioner, relies upon
couple of judgments from the Supreme Court to bring home his
point that blacklisting of a contractor cannot be done without
affording him an opportunity of being heard.
5. Having heard learned counsel for the parties, and perused the
material on record, I am of the considered view that the disputes
raised by the petitioner in this petition fall purely within the realm
of contract. The entire case of the petitioner is built on the edifice
that the impugned communication issued by the respondents is
tantamount to breach of terms and conditions of the contract. The
petitioner wants this Court to adjudicate and return a finding that
the petitioner, by not executing the contract in time, has not
breached any terms and conditions of the contract. He also wants
this Court to return a finding that the delay in completing the
works in question was attributable to the circumstances beyond his
control and, therefore, respondents should have given him enough
time to complete the works. Without commenting as to whether the
time was essence of the contract or not, as saying anything on the
issue may prejudice the petitioner, suffice it to say that this Court
in the exercise of its